Archive of case reports, events and news

 

Feb 2024

Excluding liability for dishonesty

Innovate Pharmaceuticals v University of Portsmouth (High Court) [2024]
It is often said that a contracting party cannot exclude or limit liability for fraud as a matter of public policy, but this case demonstrates that clauses can be effective to limit liability for careless and even deliberate breaches...more

Feb 2024

Liability caps and the primary obligation to pay the price

Costcutter Supermarkets v Vaish (High Court) [2024]
This case illustrates the need to ensure that any liability caps are carefully drafted taking full account of the payment structures set out in the contract ...more

Feb 2024

Relational contracts and good faith

Phones 4U v EE (High Court) [2023]
The latest word on relational contracts and the implication of general obligations of good faith...more

Nov 2023

Excluding liability for loss of profit (1)

Pinewood Technologies Asia v Pinewood Technologies (High Court) [2023]
The question before the court was whether an exclusion clause in a contract effectively excluded liability for loss of profits. The court also had to consider whether a prohibition upon exercising a right of set-off was effective. Finally, the decision also provides a useful illustration of the approach the English courts will take to applying the Unfair Contract Terms Act 1977 ("UCTA") to exclusion clauses in contracts that have been negotiated ...more

Nov 2023

Excluding liability for loss of profit (2)

Virgin Mobile Telecoms v EE (High Court) [2023]
Another case where a loss of profit exclusion had a major impact on the ability of a contracting party to claim damages ...more

Nov 2023

Scope of an indemnity

PA v Cigna Insurance (High Court) [2023]
Indemnities are now a regular feature of commercial contracts so how they are interpreted is important ...more

Nov 2023

Termination for delay

Topalsson v Rolls-Royce Motors (High Court) [2023]
Issuing a termination notice without due cause can be extremely risky as that can itself amount to a repudiatory breach. This case considered what happens where a terminating party first issues an invalid termination notice followed by a valid termination notice....more

Oct 2023

When cause of action for payment accrues
Consulting Concepts v Consumer Protection 

Assoc (SA) (Court of Appeal) [2022]
This case is a rare example of it being critical to determine exactly when a right to payment accrues due ...more

Oct 2023 Concurrent delays
Barnes v Blackburn BC (High Court) [2022]
Visits the issue of ‘concurrent’ causes of delay and the importance of following strictly the procedure for issuing notices of termination under a contract ...more
Oct 2023 Repudiatory breach
Vitol v JE Energy (High Court) [2022]
Rights to terminate a contract typically arise expressly under the terms of a contract but can also exist in parallel, at common law, for conduct which amounts to a so called ‘repudiatory breach’ ...more
Oct 2023 One capped claim or multiple capped claims?
Drax Energy v Wipro (High Court) [2023]
Great care must be taken when drafting liability limitation clauses as otherwise there is a risk of multiple parallel claims which could potentially render the limitation clause effectively redundant ...more
Jan 2023 Drafting Matters
Lawyers are always looking to ensure that any limitation of liability clauses they include are not susceptible to judicial attack. Typically they do this through the drafting of the limitation and exclusion clauses themselves. However, we recently came across what seems to be a completely novel approach involving the appointment of an arbitrator. ...more
Jan 2023 Gross negligence
Nigeria v J P Morgan (High Court) [2022]
Traditionally, English law has been slow to recognise ‘gross negligence’ as a separate and distinct concept. However, in part due to the fact that it is becoming more common for contracts to refer to the term, particularly in clauses limiting or excluding liability, the courts are now having to grapple with what the term means ...more
Jan 2023 Enforceability of liability limitations
Benkert v Paint Dispensing (Court of Sessions Scotland – Inner House) [2022]
Clauses limiting liability to specified sums are of great practical importance, particularly where the cap is comparatively small in relation to a much more significant loss. This is one area where the law does exercise a degree of oversight and so decisions, particularly from an appeal court, on when a limitation is likely to be upheld are of great importance ...more
Jan 2023 Overcoming a force majeure event
MUR Shipping v RTI (Court of Appeal) [2022]
Virtually every limitation of liability clause follows a fairly standard format, limiting the liability of a contracting party, generally the supplier or service provider, to either a specific financial sum or an amount calculated with reference to the overall or annual value of the contract in question. However, such clauses fail to address a major area of financial risk ...more
Dec 2022 Drafting Matters
Virtually every limitation of liability clause follows a fairly standard format, limiting the liability of a contracting party, generally the supplier or service provider, to either a specific financial sum or an amount calculated with reference to the overall or annual value of the contract in question. However, such clauses fail to address a major area of financial risk ...more
Dec 2022 Relational contracts – the latest word
Candy v Bosheh (High Court) [2022]
When will a contract be viewed as a ‘relational contract’?...more
Dec 2022 Interpretation of payment cap
BlackLion Law v Amira (High Court) [2022]
One would hope that a firm of solicitors should be able to craft a clear retainer. However, as this case demonstrates, even lawyers need to be careful with their drafting particularly with regard to critical payment provisions ...more
Dec 2022 Breaches capable of being remedied
Stobart Capital v Esken (High Court) [2022]
Commercial contracts, almost without exception, contain fairly standard termination provisions. These distinguish between breaches that are capable of remedy and those that are not. In the former case, termination is only allowed if, notice of the breach and an opportunity to remedy having been given, the breaching party fails to do so within the stated period. However, contracts rarely, if ever, specify which breaches fall into which category and what amounts to a sufficient remedy. One therefore has to look to the courts for guidance as to which breaches the courts consider capable of remedy and what a contracting party has to demonstrate in order to have sufficiently remedied the breach ...more
Sep 2022 Covid and the implication of terms
Bank of New York Mellon v Cine-UK and London Trocadero v Picturehouse Cinemas (Court of Appeal) [2022]
Covid and the resulting governmental lockdown restrictions had a major impact on many commercial contracts. We have previously reported on various High Court decisions on these topics. We now have the benefit of Court of Appeal judgments in two of the cases ...more
Sep 2022 Informal novation
Gama Aviation v MWWMMWM (High Court) [2022]
A novation is distinct from a simple assignment. It requires the consent of all 3 contracting parties (X, Y and Z) and it involves the original contracting party (X) being released from contractual liability and the new contracting party (Y) stepping into the shoes of X. In other words, a novation facilitates a clean break unlike an assignment where the original contracting party, X, remains fully liable for future non-performance by Y. However, seemingly, a novation involves the termination of the original contract between X and Y and the creation of a brand-new contract between Z and Y on precisely the same terms ...more
Sep 2022 Delay or inability to perform for force majeure?
NKD Maritime v Bart Maritime (High Court) [2022]
The principle of ‘force majeure’ to excuse what would otherwise constitute a contractual breach does not apply unless there is an express clause to that effect and then it is entirely dependent upon its drafting ...more
Sep 2022 The confidentiality of overheard conversations
Clearcourse v Jethwa (High Court) [2022]
Parties negotiating a contract often decide at critical points to split up into different break out rooms so that they can consider their positions in private. But what if the walls are not sound proof (as is often the case) and you overhear those private conversations? ...more
Aug 2022 Liquidated damages
Buckingham Contracting v Peel (High Court) [2022]
The inclusion of a liquidated damages regime for delays in completion can be helpful in providing certainty and clarity of remedy but only where the drafting is precise and accurate. This case also reconsidered the issue of the circumstances in which a cap on LDs can also operate as a general cap on liability for delays....more
Aug 2022 Reasonable expectations
Stichd v Force India Liquidators (High Court) [2022]
There is a well-known rule of English property law which embodies a general legal principle called ‘non-derogation from grant’, namely that, if the grantor agrees to confer a benefit on another, then the grantor should not do anything that substantially deprives the beneficiary of the enjoyment of that benefit. The judgment in the Force India case appears to be analogous with that principle....more
Aug 2022 Caps on liability and other matters from the Soteria appeal
Soteria v IBM (Court of Appeal) [2022]
Whilst the focus in the appeal in this case was naturally on the impact of the ‘loss of profit’ exclusion, the appeal court judgment had some interesting points to make on other aspects....more
Aug 2022 Take care not to waive rights of enforcement
Lombard North Central v European Skyjets (High Court) [2022]
When a dispute arises, contracting parties need to be very wary about unintentionally waiving rights. For that reason, contracts will typically include provisions aimed at ensuring that a waiver does not occur inadvertently but, as this case demonstrates, there are limits to the ambit of such clauses....more
Apr 2022 Exclusion of liability for loss of profit
Soteria v IBM (Court of Appeal) [2022]
Ever since it was issued last spring, the original High Court judgment in this case, as to the effect of a loss of profit exclusion clause, has been highly controversial and much criticised. The overturning of that decision is to be welcomed not least because it accords more with normal use of language....more
Apr 2022 Force majeure and reasonable endeavours to overcome
Mur Shipping v RTI (High Court) [2022]
Those whose contracts have been affected by the latest sanctions that have been introduced recently by many governments might be interested in this case which considered what a party might be required to do in order to be able to successfully invoke a contractual force majeure clause which required the party affected to take reasonable endeavours to overcome the force majeure situation....more
Apr 2022 Material adverse change clause in the spotlight
The FA Premier League v PPLive Sports International (High Court) [2022]
Contracts will sometimes contain a clause which is designed to protect one or maybe both parties from fundamental changes to the subject matter of the contract. This case featured one such contract and highlighted the need to pay close attention to the drafting. The case was also notable for what the judge said about ‘good faith negotiations'....more
Apr 2022 Force majeure validly invoked to terminate contract
European Professional Club Rugby v RDA (High Court) [2022]
Force majeure clauses and their operation have been brought to the forefront by the advent of Covid. This case was a relatively rare example of force majeure being successfully invoked. It is an interesting case for what the judge had to say about the motivations of the party seeking to terminate....more
Mar 2022 Wrongful termination amounted to repudiatory breach
Digital Capital v Genesis Mining Iceland (High Court) [2021]
Purporting to terminate a contract is a very serious step and not one to be undertaken lightly. Terminating wrongly can have very serious consequences and lead to a defaulting party being able to escape from an onerous contract. Remember also to consider that common law rights to terminate for very serious ‘repudiatory’ breaches may exist alongside express rights....more
Mar 2022 Dramatic victory for liability limitation
Benkert v Paint Dispensing (Rexson) (Court of Sessions) [2022]
Financial caps on liability are a key part of many commercial contracts, not least because in many cases, breaches of contract can cause financial loss which is out of all proportion to the value of the contract. Such caps on liability are one of the few provisions under English law which are, by virtue of statute, subject to judicial scrutiny and a test of ‘reasonableness’. Historically, the courts seemed to take a fairly aggressive approach to limitation clauses. In more recent times, the approach seems to be more accepting of the commercial justification behind such clauses and this is a very good example....more
Mar 2022 Frustration
New York Mellon v Cine UK (High Court) [2021]
This is another in the line of cases which have been created by the pandemic under which a party sought to claim that the pandemic had ‘frustrated’ a contract. What was quite unique in this case was the argument that contracts could be temporarily frustrated (similar to a suspension), following which they could come back to life....more
Mar 2022 Time of the essence
Pharmapac v HBS Healthcare (High Court) [2022]
As this case illustrates, time can be ‘of the essence’ even though not expressly stated as such in the documentation forming the contract. This can give rise to important rights to terminate but you must be careful not to have waived your rights....more
Jan 2022 Lessons in drafting ‘full and final’ settlements
Global Display Solutions v NCR (High Court) [2021]
This case considers the scope of a ‘full and final’ settlement and demonstrates that, in drafting terms at least, sometimes ‘less is more’....more
Jan 2022 Are legal costs within a contractual cap on liability?
Equitix Biomass v Fox (High Court) [2021]
Legal costs are always a critical factor in the decision whether or not to litigate. It is therefore, perhaps surprising that, to our knowledge, no case has, until now, ever considered the question as to whether a limit of liability applies only to the damages awarded or includes any award of legal costs....more
Jan 2022 Damages for inappropriate harvesting of personal data
Lloyd v Google (Supreme Court) [2021]
Data controllers and their data processors spend many hours discussing the allocation of risks arising from GDPR breaches. Partly, this is because of the huge potential financial risks involved both from fines and large damages claims, particularly where large numbers of data subjects are affected. This case perhaps offers some re-assurance that the courts are willing to limit applicable damages in appropriate cases and suggests that representative class actions involving many thousands of claimants will not be quite as attractive as some may have thought / feared....more
Jan 2022 The latest on all reasonable endeavours
Brooke Homes v Portfolio Property Partners (High Court) [2021]
‘Endeavours’ commitments of different varieties in contracts are commonplace but they are often recipes for uncertainty and disagreement. The courts have, as a result, had several attempts at trying to spell out what sort of commitment they represent and this case was the latest example....more
Dec 2021 Correcting mistakes in drafting
Monsolar v Woden Park (Court of Appeal) [2021]
Financial provisions within contracts are often a source of error and dispute. It is critically important to get them right as there are obvious direct financial consequences if they are not clear or if they are capable of different interpretations. The courts are more likely to intervene if the alleged error is a very extreme one ....more
Dec 2021 Impact of a loss of profit exclusion
Acerus v Recipharm (High Court) [2021]
Exclusions of liability for ‘loss of profit’ are fairly commonplace in a whole variety of commercial agreements. The courts have, however, shown an unwillingness to give effect to such clauses in circumstances where to do so would effectively deprive the innocent contracting party of any meaningful remedy....more
Dec 2021 Time bars
Arab Lawyers Network v Thompson Reuters (High Court) [2021]
A limitation clause which imposes a deadline on when claims can be brought can be very significant, since a failure by a claimant to abide by it can provide an absolute defence to the claim. In this particular case, the clause in question depended upon when the ‘basis for the claim became known’ [to the claimant]. ....more
Dec 2021 Limiting liability for wilful default
Mott MacDonald v Trant Engineering (High Court) [2021]
This case was an interim application to the court to determine a preliminary point of law as to whether a contractual limitation clause would apply to breaches of contract occurring as a result of deliberate or wilful conduct...more
Nov 2021 Software created ‘in the course of employment’?
Penhallurick v MD5 (High Court) [2021]
Section 11(2) of the Copyright, Designs and Patents Act 1998 (CDPA) provides that, where works have been created by an employee in the course of their employment, the employer will be the first owner of any copyright in the work subject to any agreement to the contrary. Questions arose in this case regarding the impact of work having been carried out at home, out of office hours and using computers not owned by the employer...more
   
Nov 2021 Damages for data security breaches
Warren v DSG Retail (High Court) [2021]
Data controllers and data processors face unprecedented financial liabilities for data security breaches both from fines imposed by regulators and potential damages claims from data subjects whose data is the subject of unauthorised access. Damages claims are particularly worrying because of the sheer number of potential claimants. This case is one of the first to consider in detail the basis and extent of such damages claims...more
   
Nov 2021 Onerous term buried in standard terms incorporated by reference not enforceable
Blu-Sky Solutions v Be Caring (High Court) [2021]
Organisations who routinely contract on standard terms published on a web site and who seek to incorporate such terms by referring to them in a sales document or order form should be aware of the perhaps little known principle of English law which featured in this case ...more
   
Nov 2021 Suspension of payment obligations due to Covid lockdowns?
Trocadero v Picturehouse Cinemas (High Court) [2021]
Covid-19 has had a critical impact on contracts just as it has on virtually all other aspects of daily life. The financial consequences have been enormous and quite unprecedented. It is therefore entirely unsurprising that the courts are now being asked to adjudicate on disputes related to the impact of the virus. In this particular case, the court had to decide whether the fact that a cinema complex had to close during a lockdown affected the liability of the tenant to continue to pay rent ...more
   
Oct 2021 Unreasonable exclusion under UCTA
Phoenix Interior v Henley Homes (High Court) [2021]
English contract law very largely respects the principle of freedom of contract, allowing commercial businesses to decide whether and upon what terms to contract, acting in their own best interests. The primary exception to this is the Unfair Contract Terms Act dating from as long ago as 1977 which requires that certain limitation and exclusion clauses must satisfy a ‘reasonableness’ test in order to be enforceable. It is therefore of critical importance for contracting parties and their advisors to be aware of the latest judgments from the courts as to when a clause might be held to be unreasonable ...more
   
Oct 2021 Liquidated damages and the impact of termination
Triple Point Technology v PTT (Supreme Court) [2021]
This case concerned the impact of validly terminating a contract for delay in circumstances where there is an active LDs provision under which LDs are accruing in respect of the delay. The Court of Appeal came to a conclusion that seemed to potentially limit the ambit and effectiveness of LD provisions in circumstances where the customer ultimately terminates. The case also looked at the relationship between LD provisions and caps on liability as well as a potential carve out from the liability cap for negligence ...more
   
Oct 2021 Liquidated damages and partial completion
Ballymore v Dobler (High Court) [2021]
It is now relatively rare for liquidated damages provisions in contracts between commercial organisations to be declared by the courts to be a penalty and therefore unenforceable. However, it does still happen occasionally, and this case might have been considered to be a possible candidate. In the long run, however, this case may be more significant for what the court also said about an LDs clause operating as a cap on liability ...more
   
Oct 2021 ‘Lawful act’ duress
Pakistan International Airline v Times Travel (Supreme Court) [2021]
This case involved questions regarding the existence and scope of so called ‘lawful act’ or ‘economic’ duress – pressure exerted in the course of the negotiation of a contract, thereby potentially entitling the party subject to the duress to rescind the contract in question. When does a particular demand made in the course of contract negotiations amount to illegitimate [unlawful] economic pressure, as opposed to the pressure of normal [lawful] commercial bargaining? ...more
   
May 2021 The broad (and unintended?) effect of a loss of profit exclusion
CIS v IBM (High Court) [2021]
Exclusions of liability for ‘loss of profit’ are routine and, historically at least, relatively uncontentious. Sellers / service providers typically included the exclusion and buyers were happy to accept it on the basis that its impact was thought to be limited. That may have changed completely as the result of this decision ...more
   
May 2021 An unenforceable penalty?
Permavent v Makin (High Court) [2021]
It is a long-established principle of English law that a provision which constitutes a ‘penalty’ is unenforceable. However, over recent years the courts have gradually chipped away at that principle and this case is the most recent example of the extent to which the courts have been prepared to uphold clauses which would almost certainly have previously qualified as a penalty ...more
   
May 2021 Interpreting indemnities
GYM PLC v GYM Offshore Wind Farm (High Court) [2020]
Indemnities seem to be extremely fashionable but, as this case demonstrates, great care needs to be taken with their drafting, particularly given that the courts will look to interpret them restrictively if there is any ambiguity as to their scope ...more
   
May 2021 Limitation of liability equivalent to ‘price paid’ held unreasonable
B A Kitchen Components v Jowat (High Court) [2021]
This case, once again, places a large number of liability limitation clauses in serious doubt regarding their enforceability and is something of a departure from recent decisions on this topic. The existence of insurance has again been elevated to be a key factor in determining the reasonableness of a limitation clause ...more
   
April 2021 Rights of set-off and their exclusion
CIS v IBM (High Court) [2021]
Rights of set-off can be incredibly important in the context of contractual disputes. For that reason, supplier drafted terms and conditions often try to exclude rights of set-off entirely whilst customer drafted contracts often try to extend rights of set-off that apply at common law and by virtue of equity. It is important to understand that there are two distinct rights of set-off each of which have their own rules and scope of application. The two rights are known respectively as ‘legal’ and ‘equitable’ set-off rights, the latter of which is much broader and arguably more valuable since it applies at an early stage before legal proceedings have commenced. The CIS case contained a very useful discussion of equitable set-off rights...more
   
April 2021 Knowledge of sub-contractor attributed to the prime?
CIS v IBM (High Court) [2021]
Performance of a contract is often dependent upon multiple sub-contractors. Contracts typically provide that the acts and omissions of the sub-contractor are deemed to be those of the prime contractor who is liable to the customer or client accordingly. Effectively, for this purpose, they are treated as being part of a single entity. However, such clauses rarely, if ever, deal with the attribution of knowledge and, perhaps they should...more
   
April 2021 Providing valid notice of a contractual claim
Dodika v United Luck Group (High Court) [2020]
Contracting parties should always strive to comply with contractual notice provisions to the absolute letter. Failure to do so may render a claim invalid or out of time and, in this case, United’s luck ran out...more
   
April 2021 ‘Manifest errors’ in dispute resolution
Flowgroup v Cooperative Energy (High Court) [2021]
An important part of a contract is the clause which determines how disputes are to be resolved. Typically, jurisdiction over disputes is given either to the courts, to an arbitrator or an independent expert. In the latter case, a typical clause will provide that the expert’s decision is ‘final and binding except in cases of ‘manifest error’’ but what exactly does that phrase mean?...more
   
February 2021 Obligations to accept contract changes?
Essex v UBB Waste (High Court) [2020]
CDespite finding that the Private Finance Initiative (‘PFI’) contract the subject of this case was a ‘paradigm example of a relational contract’, the judge went on to explain the limits of any resulting implied duty of good faith and, specifically, that such a duty did not oblige the customer having to accept significant watering down of certain fundamental contractual requirements...more
   
February 2021 Worked examples
Altera Voyageur v. Premier Oil (High Court) [2020]
Contracts often include very complex financial formulae. Sometimes they include worked, numerical examples alongside a description in words. The question to be determined is what happens when the numerical example is different from the description in words?...more
   
February 2021 Good faith
Cathay Pacific v Lufthansa (High Court) [2020]
The latest chapter in the ongoing see-saw saga of ‘good faith’ and ‘relational contracts’...more
   
February 2021 Making time of the essence
Alegrow v Yayla Agro (High Court) [2020]
‘Time of the essence’ is a common phrase in commercial contracts, but it is frequently misused. It is often not appreciated that time of performance will not be ‘of the essence’ unless explicitly made so. Questions then arise as to how ongoing delays in performance can be sufficient to justify termination...more
   
September 2020 A duty to act ‘rationally’
UK Acorn Finance v Markel (High Court) [2020]
In some cases, a contracting party may be obliged to demonstrate that it has acted ‘rationally’ when taking decisions in relation to contracts ...more
   
September 2020 Multiple contracts and the recovery of profit
Attorney General Virgin Islands v Global Water (Privy Council) [2020]
This case considered the ability of a contractor to recover damages in respect of lost profits in circumstances where its appointment was split into distinct contracts covering different stages of the relationship ...more
   
September 2020 Grounds for withholding consent
Apache North Sea v Ineos (High Court) [2020]
Contracts routinely make certain matters ‘subject to the prior consent of [the other contracting party], such consent not to be unreasonably withheld’ The question in this case was whether consent had been withheld on reasonable grounds ...more
   
September 2020 Be clear who your client is.
RSK Environment v Hexagon Housing (High Court) [2020]
Claims for damages can be brought both for breach of contract and, in tort, typically for negligence i.e. a failure to exercise reasonable skill and care in circumstances where a duty of care is held to exist. Often, claims in both contract and tort subsist in parallel but the right to bring a claim for negligence can exist independently of there being any contract in place between the claimant and defendant provided a duty of care is held to exist. The question to be answered here was whether limitation clauses in a contract applied to a claim brought by an entity that was not a party to the contract in question? ...more
   
July 2020 Failures by procuring body render public sector contract void.
School Facility Management v Christ the King College ( High Court) [2020]
This case raises potentially very significant concerns for suppliers and service providers to the public sector (and beyond) ...more
   
July 2020 Don’t delay if relying upon an indemnity
Towergate v Hopkinson (High Court) [2020]
A recent case in the Court of Appeal has highlighted the importance of strictly adhering to express contractual conditions when seeking to rely on an indemnity clause ...more
   
July 2020 Cabinet Office Guidance on responsible contractual behaviour
Cabinet Office Guidance on responsible contractual behaviour in the performance and enforcement of contracts impacted by the Covid-19 emergency was published on the 7th May and will be reviewed again before 30th June. It suggests that contracting parties should act ‘responsibly and fairly’ in their responses to issues caused by the virus. This phrase appears multiple times in the Guidance (ten times over only five pages) but there is very little detail as to what exactly that would entail. The Guidance does however ...more
   
July 2020 Suspension of termination rights on insolvency
Following public consultation and the UK Government’s response published in August 2018, on 20 May 2020, the Government published the Corporate Insolvency and Governance Bill (“CIGB” or the “Bill”). This Bill, as well as having broader corporate implications, also has significant impacts on commercial contracts ...more
   
June 2020 Entire Agreement clauses and contract interpretation
NHS v Vasant (Court of Appeal) [2019]
So called ‘entire agreement’ clauses are a familiar part of contractual ‘boilerplate’. As their name would suggest, they are intended to make clear that the executed written document is the entire agreement between the parties ...more
   
June 2020 Another look at concepts of ‘consequential’ loss and ‘force majeure’
2 Entertain v Sony (High Court) [2020]
‘Consequential loss’ is a legal phrase that has perplexed and mystified lawyers and their clients for many years. Several cases have analysed the meaning of the phrase in order to ascertain whether an entitlement to damages is either restricted or even excluded altogether. This case is the latest example.

The case also looked at the topical principle of ‘force majeure’ in the context of a riot and a resulting fire. ...more
   
June 2020 Wrongful termination for ‘substantial breach’
PBS Energo v Bester (High Court) [2020]
If a contracting party wrongly purports to terminate a contract when they do not have sufficient grounds for doing so, there is a clear danger that they will themselves be committing what is known as a ‘repudiatory breach’. Such a breach will entitle the other contracting party to ‘accept’ that repudiation and terminate themselves, thereby completely turning the tables. This could render the party who originally purported to terminate liable for damages as well as substantially reducing or even eliminating any claim for damages that they might have had relating to the breach(es) which formed the basis of the original purported termination. Termination is therefore a very high-risk option unless you are on very firm ground ...more
   
June 2020 Company not vicariously liable for acts of employee
Morrison Supermarkets v Various Claimants (Supreme Court) [2020]
The Supreme Court has handed down a very important judgment for all data controllers and processors who were concerned that they could be strictly liable in damages for data security breaches even where the acts of the employee in question were done very deliberately to damage the employer ...more
   
January 2020 Reasonable endeavours
Gaia Ventures v Abbeygate (Court of Appeal) [2019]
Many contracts routinely contain obligations to ‘endeavour’ to do something. These seem to give rise to disputes quite frequently as to the precise extent of the obligation. This case is the latest example ...more
   
January 2020 Auto generated email footers as ‘signatures in writing’
Neocleous v Rees (County Court) [2019]
A contract for the sale or other disposal of an interest in land must satisfy the requirements of section 2 of the Law of Property (Miscellaneous Provisions) Act 1989 namely the contract must be in writing and signed by or on behalf of each party to the contract. In this respect the statutory provision is essentially the same as many contractual provisions that require a contract to be signed in order to be enforceable and require variations to be in writing and signed on behalf of both parties. The question was whether an automatically generated email footer containing the name and contact details of the sender constituted a signature ...more
   
January 2020 Implied duties of good faith
New Balance v Liverpool (High Court) [2019]
The English courts have traditionally been very reluctant to imply duties of good faith into contracts governed by English law but this attitude seems to have changed significantly over recent years to the point where contracting parties seem to readily accept that such a term will often be implied. This is one such example where the court’s role was to determine what such an implied term required of the parties ...more
   
January 2020 Repudiation of a contract
Sanderson v Simton Food (High Court) [2019]
‘Repudiation’ [of a contract] is the term which describes the conduct of a contracting party which entitles the other to treat the contract as terminated at common law. Such a right to terminate can exist independently of express contractual rights to terminate ...more
   
December 2019 Identified third parties and rights to enforce contracts
Chudley v Clydesdale Bank (Court of Appeal) [2019]
Up to the year 2000, only the parties to a contract could acquire directly enforceable rights or obligations under it. This was the rule of privity of contract. The situation was changed by the Contracts (Rights of Third Parties) Act 1999 (Third Party Rights Act). One of the requirements of the Act is that for a third party or parties to acquire the right to enforce a contract they must be ‘expressly identified’ either by name or as a member of a class ...more
   
December 2019 Excluding rights of set-off and when sums are due
AMC III Purple v Amethyst Radiotherapy (High Court) [2019]
Rights of set-off are, as the term suggests, rights to ‘set-off’ one counterclaim or possibly just monies owed against another primary claim. Two rights of set-off exist under English law namely ‘legal set-off’ and ‘equitable set-off’. Legal set-off is only available during the course of active litigation and only in respect of quantified sums. Equitable set-off on the other hand is, in some respects, more flexible. Equitable set-off is available outside the context of litigation where the cross-claim arises from the same transaction (or a closely related transaction) as the debt owed. Importantly, equitable set-off can apply to a claim which is unliquidated (i.e. uncertain) but ‘provisionally quantified’. Typically, suppliers and service providers routinely exclude rights of set-off in order to ensure that customers cannot withhold payment in the event of a dispute arising ...more
   
December 2019 Contract interpretation
Network Rail v ABC (High Court) [2019]
There have been a number of very senior decisions by the courts over the last few years which have helped to clarify the rules governing contract interpretation. This case does not alter the law but is an illustration of the application of the law in practice ...more
   
December 2019 Contractual condition, warranty or an innominate term?
Ark Shipping v Silverburn (Court of Appeal) [2019]
The traditional classification of contractual provisions into ‘conditions’ and warranties’ is now of much less importance than it was historically. This case is an example of how the courts are reluctant to sanction termination and will use the tool of classifying a term as an innominate one as a means to reach that position. Innominate (or sometimes ‘intermediate’) terms are ones that are neither conditions or warranties but instead can be treated as either depending upon the consequences of a particular breach ...more
   
October 2019 Beware work starting with negotiations incomplete
Anchor 2020 v Midas Construction (High Court) [2019]
Projects very often commence with contractual negotiations ongoing. This case is yet another example of the dangers of this and the uncertainties this can cause ...more
   
October 2019 Rectification for common mistake
FHSC v Glas (Court of Appeal) [2019]
Rectification is an equitable remedy by which the court may amend the terms of a legal document which, because of a mistake, fails accurately to reflect the intention of the parties to it. ...more
   
October 2019 Economic duress and exercising contractual rights
Times Travel v Pakistan International Airlines (Court of Appeal) [2019]
This case provides an interesting contrast to the Bates case we featured in June albeit that no cross reference is made to the Bates judgment and none of the arguments raised in Bates were used here. Instead, on facts which have a significant overlap on a number of key points, the arguments centred upon whether the excise of a contractual right of termination could amount to economic duress ...more
   
October 2019 The ‘blue pencil’ test
Tillman v Zehnder (Supreme Court) [2019]
A restrictive covenant will be void for being in restraint of trade unless there is a legitimate interest to protect and the protection sought is no more than is reasonable having regard to the interests of the parties and the public interest. It is generally the case that a provision which goes too far will be declared unreasonable and therefore unenforceable in its entirety. That is unless the so called ‘blue pencil’ can be applied successfully ...more
   
September 2019 Take great care when drafting contractual notices
Stobart Group v Stobart (Court of Appeal) [2019]
Another useful reminder that very great care must be taken when drafting (and serving) notices pursuant to a contract. Failure to do so may invalidate the notice and deprive a contracting party of a very valuable claim ...more
   
September 2019 ‘Extreme’ exclusion of liability upheld
Difference v Unitel (Sheriff Court) [2019]
Limitation and exclusion of liability clauses are highly contentious and in many commercial contracts, fiercely negotiated They need to be very carefully drafted to ensure that they are effective at excluding or limiting liability as intended and to ensure that they will stand up to judicial scrutiny. There are several examples over recent years where clauses have sought to go too far and have been declared unreasonable and therefore unenforceable. At first glance that seemed a distinct possibility in this case ...more
   
September 2019 Heads of Terms as a binding contract
Green Deal Marketing v Economy Energy Trading (High Court) [2018]
Heads of Terms are routinely used as a basis for negotiating a substantive contract document but as this case illustrates, they can easily become the contract itself if the parties act on them and do not ultimately conclude a more formal document ...more
   
September 2019 The latest on ‘penalty’ provisions
Simantob v Shavleyan (Court of Appeal) [2019]
This case raises issues relating to the question of penalties and what, mutual consideration or value is required, if any, in order to make the variation of a contract binding ...more
   
July 2019 Evidence of pre-contract negotiations and the exclusionary rule
Merthyr (South Wales) v Merthyr Tydfil Borough Council, (Court of Appeal) [2019]
It is an often quoted principle of English contract law that evidence of pre-contract correspondence is not permitted to be used as an aid to contract interpretation. However, despite this, such evidence is often admitted even if, in this particular case, the court was unwilling to do so ...more
   
July 2019 Recovery of group company losses
Nederlandse Industrie Van Eiprodukten v Rembrandt Enterprises, (Court of Appeal) [2019]
In the vast majority of cases contracts are entered into by corporate customers for the benefit of their group. Equally, suppliers will often enter contracts through a single representative company but with different companies within the group playing an active role in the performance of the contract whilst generating a share of the profits at the same time. In both scenarios group companies will incur losses if the contract is wrongly terminated and this case considered the extent to which such losses can be recovered in the absence of an express provision to that effect ...more
   
July 2019 Ostensible authority of those who represent a company
Stavrinides v Bank of Cyprus (High Court) [2019]
Questions are often raised about whether a contracting party is able to rely upon the signature of the individual purporting to bind the contracting counterparty. This case deals with just that issue ...more
   
July 2019 Rectification for common mistake
Persimmon Homes v Hillier (Court of Appeal) [2019]
The case acts as a reminder that, although pre-contractual correspondence is not admissible as an aid to interpreting a contract, it can be important evidence if the court is considering a claim for rectification. Where rectification is sought on the basis of common mistake, the claimant must establish that the parties’ negotiations clearly demonstrated an apparent common continuing intention, which was not properly reflected in the written agreement as a result of a mutual mistake. ...more
   
June 2019 ‘Relational’ contracts and duties of good faith
Bates v Post Office [2019]
English law has traditionally resisted implying an obligation on the parties to act in 'good faith' into commercial contracts. However, over the last few years the English Courts have, in isolated cases, been prepared to imply such a duty into so called 'relational’ contracts. The latest of these cases provides further guidance on the circumstances in which a contract may be classified as a 'relational’ contract ...more
   
April 2019 Brexit and frustration of a contract
Canary Wharf v European Medicines Agency [2019]
In the context of the ongoing Brexit negotiations, issues were always going to arise as to the effect of Brexit on ongoing commercial contracts. This was the first case of its kind where the EMA tried to claim that its long lease in respect of offices at Canary Wharf had been frustrated by Brexit ...more
   
April 2019 Implied terms
Bou-Simon v BGC Brokers (Court of Appeal) [2018]
Another case focussing on the rules governing when terms will be implied into a commercial contract. This case had an interesting twist as the court had to consider the relevance of words that had been deleted in previous drafts of the agreement during the negotiation process ...more
   
April 2019 Heads of Agreement
CRS v McLaren Automotive [2018]
Heads of Agreement (under whatever title or guise) are a commonly used mechanism to enable work to commence whilst more formal and comprehensive legal documentation catches up. However, there are dangers to such an approach as CRS and McLaren discovered to their ...more
   
April 2019 Liquidated damages and termination
Triple Point Technology v PTT [2019]
Liquidated damages provisions are quite common as a way of compensating a customer for delay and providing some incentive to perform on time. This case featured the interaction between a liquidated damages provision and the termination of the Agreement ...more
   
January 2019 Agreements to agree
Morris v Swanton Care (Court of Appeal) [2018]
‘Reasonable’ is perhaps the contract drafter’s favourite word. It is often used as a form of compromise. However, as this case demonstrates it does have its limitations ...more
   
January 2019 Liquidated damages, force majeure and ‘guarantees’
GPP Big Field v Solar EPC Solutions (High Court) [2018]
This case involved a number of topical issues including whether a ‘guarantee’ clause was, in reality, an indemnity and therefore subject to different legal principles ...more
   
January 2019 Entire Agreement clauses - enforceability
First Tower Trustees v CDS Superstores (Court of Appeal) [2018]
Entire Agreement clauses are under attack from two different directions. The Al-Hasawi case focussed on the drafting but even if you get the drafting right there is still a risk that the clause will be held to be unreasonable and therefore unenforceable. This was the focus of this second case ...more
   
January 2019 Entire Agreement clauses – scope and effect
Al-Hasawi v Nottingham Forest Football Club (High Court) [2018]
‘Entire Agreement’ clauses are routinely inserted into contracts with little or no thought. Their aim is to ensure that the written contract is the sole record of the parties’ rights and obligations. In recent years, time and again the courts have, however, found ways of circumventing the drafting where it was considered appropriate and this is yet another example ...more
   
November 2018 Contract formation and limitations of liability
Arcadis Consulting v AMEC (Court of Appeal) [2018]
We previously reported on this case back in December 2016 (see http://www.trglaw.com/news217.html) when the High Court decided that because of the way in which the contract between the parties had been formed no limitation of liability had been effectively incorporated into the contract. The Court of Appeal has now reconsidered the case ...more
   
November 2018 Vicarious liability for data security breaches
Morrison Supermarkets v Various Claimants (Court of Appeal) [2018]
The Court of Appeal has upheld a decision that could make employers vicariously liable for their employees’ actions even if they have taken every conceivable preventative step and bear no criminal responsibility. The court upheld a High Court ruling that supermarket chain Morrisons was liable for the actions of former employee Andrew Skelton. Morrisons said it will appeal to the Supreme Court ...more
   
November 2018 Penalty clauses
Holyoake v Candy (High Court) [2018]
This case demonstrates how careful drafting can avoid the operation of the rule against penalties ...more
   
November 2018 Force majeure and reasonable endeavours
Seadrill v Tullow (High Court) [2018]
Force majeure (literally ‘superior force’) is a well-known legal phrase that is often bandied about in connection with commercial contracts but it is not particularly well understood. It is comparatively rare for it to be the subject of a reported case ...more
   
November 2018 Copyright ownership and software
Sprint Electric v Buyer’s Dream (High Court) [2018]
The first owner of copyright in a new computer program will, typically, be the creator irrespective of whether the creator has been paid by somebody else to develop it. The one exception to this is the relationship of employer and employee where the employer automatically owns copyright in works created by an employee in the course of employment ...more
   
November 2018 Meaning of ‘shall’
PM Law v Motorplus (Court of Appeal) [2018]
According to a well-known dictionary ‘shall’ means (amongst other things) “expressing an instruction, command, or obligation”. This case revolved around the meaning of the term when used in a contract ...more
   
November 2018 ‘Concurrent delays’
North Midland v Cyden (Court of Appeal) [2018]
It will often be the case that delays are not caused just by one reason. This case concerned an example of so called ‘concurrent delays’ i.e. delay caused by two or more reasons acting at the same time ...more
   
November 2018 Software as goods
Computer Associates v The Software Incubator (Court of Appeal) [2018]
The Commercial Agents Regulations 1993 (the Regulations) give certain rights to commercial agents particularly on termination of the appointment. The Regulations only apply to agents who sell goods on behalf of a principal. They do not apply to the sale of services. The Regulations do not, however, provide a definition of ‘goods’. What constitutes ‘goods’ is important for a variety of reasons, not least, whether certain implied conditions under Sale of Goods legislation might apply...more
   
October 2018 Express good faith clause and competing businesses
Health & Care Management v Physiotherapy Network [2018]
Express ‘good faith’ clauses are becoming much more common in commercial contracts governed by English law. Some like the principle they reflect whilst others feel that they introduce an element of uncertainty. Here is an example of a good faith clause coming to the rescue in circumstances where contract drafting on a particular topic was otherwise deficient...more
   
October 2018 Excluding liability for loss of profit
Motortrak v FCA Australia [2018]
Commercial contracts routinely exclude liability for ‘loss of profit’. This case demonstrates some potential dangers for a contracting party where a mutual exclusion for loss of profits has been included in a contract. The case is also notable for observations on when delays in terminating will amount to an affirmation of a contract (thus precluding termination on the basis of a repudiatory breach) and also when invoices become (a) due and (b) payable...more
   
October 2018 Withholding approval
Redbourn v Fairgate [2018]
This case illustrates that express contractual rights of termination will rarely be exhaustive and sheds some light as to the basis upon which a contracting party can legitimately withhold approval in circumstances where the contract counterparty is specifically obliged to obtain approval ...more
   
October 2018 Oral variations
Rock Advertising v MWB Business Exchanges (SC) [2018]
We reported on the Court of Appeal decision back in our September 2016 Update. The Court of Appeal had overturned the original decision of the County Court. Now the Supreme Court has in turn overruled the Court of Appeal, effectively giving legal effect to contractual clauses which prohibit oral variations to a commercial contract having effect ...more
   
June 2018 Vicarious liability
Frederick v Positive Solutions (CA) [2018]
This case involved the law concerning when a business will be vicariously (strictly) liable for the acts of an agent. Most cases involving vicarious liability concern employees so in this respect the case was unusual. The decision in this case is particularly interesting given the previous judgement in the Morrison’s data protection case which we featured back in January [link]. Here the Court of Appeal took a more traditional approach to the scope of vicarious liability ...more
   
June 2018 Interpretation of a long term ‘relational’ contract
Amey v Birmingham City Council
Another case which touches upon whether ‘relational contracts’ (whatever they may be) are truly in a category of their own when it comes to contractual interpretation...more
   
June 2018 Joint ventures and an implied duty of good faith
Al Nehayan v Kent
Cases where arguments founded on an implied obligation of good faith rarely succeed but this is an example where such an argument was successful on the facts...more
   
June 2018 Consent not to be unreasonably withheld
Crowther v Arbuthnot
Commercial contracts routinely require a contracting party to obtain the consent of their counterparty to a particular act. Again, typically, such provisions expressly state that consent cannot be unreasonably withheld. This case looked at what this means...more
   
March 2018 EVENT: HOT TOPICS IN COMMERCIAL CONTRACT LAW
We organised our annual seminar in conjunction with the IACCM (International Association for Contract and Commercial Management) on 15th March 2018. The event covered issues such as liability caps and indemnity provisions, the General Data Protection Regulation (GDPR) and implied contractual duties with an open forum Q&A.
   
January 2018 Interpretation of liability clause reconsidered
ROYAL DEVON AND EXETER NHS FOUNDATION TRUST v ATOS (CA)
The Court of Appeal reconsidered the interpretation of a clause seeking to limit liability and reversed the original Court’s decision. It found that a contractor's liability clause imposed two separate caps on liability rather than a single limit...more
   
January 2018 When are remedies for breach of contract exclusive?
HARCAP v F K GENERATORS
Contracting parties are unlikely to intend to cut down the remedies which the law provides for breach of important contractual obligations and so make them exclusive remedies, without using very clear words having that effect. This was the Court’s conclusion in a case where a fee was payable for breach of contract and so this did not mean the injured party had no other remedies...more
   
January 2018 Opportunity to remedy breach before termination
INTERSERVE v HITACHI
The Court granted a declaration that a contractor ought to have been given the opportunity to remedy its breach of contract before its engagement was ended...more
   
January 2018 Employer liable for employee’s data breach
VARIOUS CLAIMANTS v MORRISONS
This was a group action which concerned the issue of whether an employer was liable, directly or vicariously, for the actions of a rogue employee who had disclosed personal information of co-employees on a website. Could the employer be liable under the Data Protection Act 1998, for an action for misuse of private information and/or for breach of confidence?...more
   
December 2017 Exercising discretion rationally
BHL v LEUMI
This is a useful example of how contractual parties should exercise discretion in contracts. The Court found that a lender had not behaved rationally when exercising its contractual discretion to charge certain fees so it had to refund the fees charged which were considered to be excessive...more
   
December 2017 Fitness for purpose
MT HØJGAARD v E.ON CLIMATE (SC)
The Supreme Court upheld a customer’s appeal and found that a contractor was liable to comply with a fitness for purpose type obligation which took priority over a duty to comply with an international standard. This may have significant consequences for the interpretation of complex project contracts, which often incorporate technical schedules and other specification documents...more
   
December 2017 Contractual right or discretion needed?
SHURBANOVA v FOREX CAPITAL MARKETS
This case looked at when a party can exercise an absolute contractual right or whether it has to use its discretion in a fair way in applying a contractual right...more
   
December 2017 Identifying third parties who can enforce contract terms
CHUDLEY v CLYDESDALE BANK
The Court set out its approach to identifying third parties who can enforce contract terms where they are not named in the contract. Before the Contracts (Rights of Third Parties) Act 1999,  only the parties to a contract could enforce its terms (the so-called ‘privity of contract’ rule). The 1999 Act changed all that although it is relatively rare for cases to look at how the 1999 Act operates...more
   
November 2017 Unclear liability clause enforceable
ROYAL DEVON AND EXETER NHS FOUNDATION TRUST v ATOS
The Court considered whether an unclear limitation of liability clause was enforceable and also whether a claim for wasted expenditure amounted to a claim for loss of profit or revenue which was excluded under the contract...more
   
November 2017 Granting or withholding consent
WATSON v WATCHFINDER
This case looked at whether there was an implied duty on directors not to act unreasonably, capriciously or arbitrarily in deciding whether to give their consent to the exercise of a provision in an option agreement or whether the company’s board had an absolute veto over the exercise of the option...more
   
November 2017 Implied ‘duty to speak’
TED BAKER v AXA INSURANCE (CA)
The Court of Appeal found that an insurer had an implied ‘duty to speak’ to tell its customer that certain material it had requested for the purpose of investigating claims from the customer was outstanding. In the circumstances, the customer was entitled to expect that, if the insurer regarded the material as still to be provided, then, acting honestly and responsibly, it should have said so and not to do so was misleading...more
   
November 2017 Implied ‘duty to co-operate’
TAKEDA PHARMACEUTICAL COMPANY v FOUGERA
The Court considered whether the seller was subject to an express or implied obligation under the terms of an SPA to provide certain information to the buyer. This case suggested that if a contracting party wants co-operation from another party, it needs to draft an express provision into the agreement...more
   
September 2017 Implied duties not to prevent performance and to co-operate
WILD DUCK v SMITH
It was confirmed that generally terms will be implied into a contract that neither party will prevent or delay the other from carrying out its obligations under it and that the parties will co-operate to make the contract work, although the extent of that duty should not be exaggerated...more
   
September 2017 The importance of giving notice of assignment
GENERAL NUTRITION INVESTMENT v HOLLAND AND BARRETT
Some notices of termination served by the party to whom a trade mark licence was assigned were found to be invalid because no notice of the assignment had been given to the licensee before they were issued...more
   
September 2017 Reasonable endeavours
MINERVA v GREENLAND
This case showed that where the parties have handled negotiations competently and appropriately having regard to the time available, the Court is likely to find that they have met an obligation to use ‘reasonable endeavours’ to achieve a particular outcome...more
   
September 2017 Passing on responsibility for criminal offences
GEDDES v JOHNSON
This Scottish decision suggests that there are certain limits to a well-established principle of English law which prohibits criminal penalties being passed to another, insurance being taken out against the risk of such penalties or seeking an indemnity against having to pay penalties. It was decided that in some circumstances a third party could find itself liable for another’s criminal penalty...more
   
July 2017 Exclusion clauses and the contra proferentem rule
PERSIMMON HOMES v OVE ARUP (CA)
Courts have traditionally been hostile to clauses limiting or excluding liability and have used a range of methods to defeat what might at first sight seem to be wide-ranging exclusions. The old principle of contra proferentem (where a clause is interpreted restrictively against the party who introduced the wording in question or who was seeking to place reliance upon it) is one of the favoured tools. However, the Courts appear to be more prepared to give effect to the words used by the parties and to apply the contra proferentem rule less...more
   
July 2017 Implied variation/term of good faith
IRKERLER OTOMOTIV v PERKINS ENGINES (CA)
A claim that a variation to one part of a contract had amended another part was dismissed by the Court of Appeal which also refused to imply a term of good faith when one party was terminating a contract without cause...more
   
July 2017 Interpretation of performance mechanism
SUTTON HOUSING PARTNERSHIP v RYDON MAINTENANCE (CA)
Many services contracts include mechanisms to measure performance and worked examples of how such mechanisms are intended to operate are often set out. In this case, the Court of Appeal found that ‘example’ figures given in a contract in relation to a performance mechanism were intended to be binding and of general application rather than being merely illustrative...more
   
July 2017 Service of contractual notices
HOE v ANDERSEN
The Courts have always traditionally been very strict on insisting that in order to be valid, contractual notices must be served precisely in accordance with the provisions of any notice clause. This Scottish case represents the first time a senior Court has taken a more pragmatic approach and begins to offer some hope for those who do not precisely follow the requirements of a notice clause...more
   
June 2017 Exclusion of all liability for negligence
GOODLIFE FOODS v HALL FIRE PROTECTION
One of the first things that lawyers are taught is that under English law it is not possible in a contract to exclude liability for death or personal injury caused by negligence. For that reason the vast majority of exclusion clauses make clear that they do not impact such liability. The question is, what happens when the clause does not make that clear?...more
   
June 2017 Scope of costs covered by an indemnity
EURO ASIAN OIL v CREDIT SUISSE
The scope of an indemnity is entirely dependent upon its precise wording as this case amply demonstrates...more
   
June 2017 Interpretation of an indemnity clause
WOOD v CAPITA INSURANCE (SC)
This is another case concerned with the scope of an indemnity. In 2015, the Court of Appeal found that on the proper interpretation of an indemnity in a share purchase agreement, no liability arose because the trigger event had not occurred. The decision was the subject of a further appeal to the Supreme Court...more
   
June 2017 Deciding new contract terms by arbitration
ASSOCIATED BRITISH PORTS v TATA
It is well known that ‘agreements to agree’ are unenforceable. This case sought to avoid such a vacuum by referring a failure to agree terms to an arbitrator to decide how certain contract provisions were to be varied and apply throughout the remainder of the agreement. The question was whether such a mechanism was effective...more
   
May 2017 The impact of the General Data Protection Regulation - update
To mark one year until the GDPR is implemented, on 25th May 2017 the ICO published some further updates setting out what guidance organisations can expect to help them prepare for compliance with the GDPR's requirements before May 2018, and in particular to assist them with planning what areas to address over the coming months...more
   
May 2017 Correction of a mistake
MILTON KEYNES BOROUGH COUNCIL v VIRIDOR
Contracts are often negotiated and rushed through to completion in a great hurry to meet an urgent deadline. There is always a fear, particularly where multiple drafts are involved, that the parties will use the wrong document when the time for signature comes. This case should provide some comfort that if such a mistake is made, the Courts will correct the position in appropriate circumstances...more
   
May 2017 Meaning of ‘all’ and ‘any’
DOOBA DEVELOPMENTS v McLAGAN INVESTMENTS
As contract drafters will be all too well aware, the ‘devil is in the detail’ and none more so than here where the Court had to decide what some ambiguous wording meant...more
   
May 2017 Subject to contract
GLOBAL ASSET v AABAR (CA)
The heading ‘subject to contract’ is often used on documents to try to show that the parties do not intend to be legally bound because they are still in the process of negotiation and have not yet finalised their agreement, or that the agreement they have reached is not to be binding until it is signed. Here the Court of Appeal had to decide what the impact of subsequent telephone conversations had been which followed a ‘subject to contract’ offer letter...more
   
May 2017 Implied terms and express provisions
IRISH BANK RESOLUTION CORPORATION v CAMDEN (CA)
The Court of Appeal was asked to consider the basis for implying terms into a contract in circumstances where the term sought potentially conflicted with or restricted an express term of an agreement...more
   
April 2017 Consent to use data under the GDPR
The Information Commissioner’s Office issued some draft guidance on consent to use data under the General Data Protection Regulation in March 2017. It is designed to help organisations decide when to rely on consent for processing and when to look at alternatives. It explains what counts as valid consent and how to obtain and manage consent in a way that complies with the GDPR...more
   
April 2017 Financial claims falling within a liability cap
McGEE v GALLIFORD TRY BUILDING
All of a contractor’s financial claims for delay caused by a sub-contractor were found to be capped at 10% of the value of the sub-contract...more
   
April 2017 ‘All reasonable endeavours’
ASTOR MANAGEMENT v ATALAYA MINING
The effect of an express obligation to use ‘all reasonable endeavours’ was considered and it was concluded that where an express term exists, there was no need or scope to imply a lesser term requiring the party to act in good faith...more
   
April 2017 An unenforceable ‘agreement to agree’
TEEKAY TANKERS v STX OFFSHORE AND SHIPBUILDING
An agreement by which an option was granted to purchase ships was held to be unenforceable. The agreement provided that the delivery date for the ships was to “be mutually agreed”. This was considered to be an ‘agreement to agree’ and the express wording meant that it was not possible to imply a term to give the agreement sufficient certainty to make it enforceable...more
   
April 2017 Express obligations of ‘mutual trust and co-operation’
COSTAIN v TARMAC
This case featured the NEC form of model construction contract and contained an express obligation that both parties had to act in a spirit of ‘mutual trust and co-operation’. The decision for the Court was what impact this obligation had on other specific contractual provisions...more
   
April 2017 Extent of meaning of ‘consequential loss’
JAY JALA v DDG CONSTRUCTION
(US District Court of Pennsylvania)
The meaning of ‘consequential loss’ has different meanings to different lawyers and it has sometimes been given a much broader interpretation in the US, as this case illustrates. It demonstrates why a supplier would certainly want to contract under US law and a customer would want to contract under English law...more
   
April 2017 The impact of the General Data Protection Regulation - update
The ICO published an update setting out what guidance organisations can expect to help them prepare for compliance with the GDPR's requirements before May 2018, and in particular to assist them with planning what areas to address over the coming months...more
   
March 2017 Potential impact of Brexit on commercial contracts - update
It is unclear what will happen when the UK leaves the EU. However, we have put together some thoughts on the impact the Brexit decision might have on commercial contracts which we hope might be useful...more
   
January 2017 Wide meaning given to exclusion of ‘consequential or special losses’
STAR POLARIS v HHIC-PHIL
The Court gave a much wider meaning to an exclusion of liability for “any consequential or special losses” than is usually the case. It decided that the parties had exhaustively agreed the categories of loss which were to be recoverable and that liability was therefore excluded for all other losses...more
   
December 2016 Contract/no contract - case with a sting in its tail
ARCADIS CONSULTING v AMEC
This decision was described as a relatively straightforward 'contract/no contract' case with ‘something of a sting in its tail’. The Court found that despite various terms and conditions being exchanged between the parties as part of discussions in relation to work which was then carried out, only a simple contract existed between the parties under which the consultant’s liability was uncapped...more
   
December 2016 Interpretation of exclusion clause
IMPACT FUNDING v AIG (SC)
The Supreme Court confirmed some established principles in relation to the interpretation of contracts. This case related to a restriction in the scope of a firm of solicitors’ professional indemnity insurance policy and provides some useful reminders of the principles applicable to the interpretation of contracts generally...more
   
December 2016 Meaning of ‘fitness for purpose’
FLUOR v SHANGHAI ZHENHUA
The Technology and Construction Court held that a supplier was in breach of a warranty to supply goods which were fit for purpose...more
   
December 2016 Common law right to terminate and failure to pay
GRAND CHINA v SPAR SHIPPING (CA)
Whilst this case featured a shipping contract between a ship owner and some traders for the hire of some ships, some interesting points were made in relation to the rights of termination that apply to commercial contracts generally in the context of repeated late payment...more
   
September 2016 Case update
The cases featured are useful reminders of the principles established in earlier decisions. They cover subjects such as the importance of serving notices strictly in accordance with the terms of the agreement; the difficulties of claiming that a breach of warranty is also a misrepresentation; whether termination clauses must be invoked in good faith; restrictions on the right of an innocent party to affirm a contract and continue claiming liquidated damages and the effectiveness of an oral variation…more
   
September 2016 FCA guidance for outsourcing to the ‘cloud’
The Financial Conduct Authority published some guidance in July 2016 to clarify the requirements for regulated businesses when outsourcing to the ‘cloud’ and other third party IT services. The FCA guidance is not legally binding. However, regulated businesses are expected to take note of it and, where appropriate, use it to inform their systems and controls on outsourcing…more
   
September 2016 New EU framework for electronic signatures
Electronic signatures are a way to sign ‘virtual’ documents, much like a pen is used to sign a hard-copy document. The traditional practice of signing a hard-copy document in ink, scanning it and sending it by email is being overtaken by the use of e-signatures as these become increasingly common in a range of commercial transactions. Some new Regulations which establish a new EU-wide framework for e-signatures came into force on 22nd July 2016. Previously all countries in the EU had their own individual e-signature laws but now standards across the EU will be the same…more
   
September 2016 EU-US Privacy Shield - update
The so-called EU-US ‘Privacy Shield’ is an alternative means of authorising data transfers to the US and entered into force on 1st August 2016. It allows for transfers from a data controller or data processor in the EU to self-certified US companies following the declaration in October 2015 that the old 'Safe Harbor' framework did not provide adequate protection for transfers of individuals' data to the US…more
   
July 2016 Effectiveness of requirement for written variations of contract
GLOBE MOTORS v LUCAS VARITY (CA)
Including a clause that any variation of the contract should be in writing may not prevent subsequent variation of the contract orally or by conduct as illustrated in this decision...more
   
July 2016 Definition of consequential loss included wasted ‘spread costs’
TRANSOCEAN DRILLING UK v PROVIDENCE RESOURCES (CA)
Some mutual indemnities applicable to both parties were upheld, with the result that a contractor succeeded in excluding liability for certain wasted costs under consequential loss as defined in the contract. The Court of Appeal relied on the plain meaning of the wording and did not apply restrictive principles of interpretation, commonly used to cut down the effect of limitation clauses...more
   
July 2016 Obligation to allow an opportunity to remedy before terminating
VINERGY INTERNATIONAL v RICHMOND MERCANTILE
The High Court considered whether a requirement that a party wishing to terminate for contractual breach must give an opportunity to remedy the breach applied when the party was terminating not based on the contractual provision but under separate ‘common law’ rights for repudiatory breach...more
   
July 2016 Liability under a warranty and for misrepresentation
WEMYSS v KARIM (CA)
There are different measures for calculating damages depending on, for example, whether the claim is for a breach of warranty in contract or for misrepresentation (a false statement made before a contract on which a party relies when entering into a contract). Where both claims are available, a party is free to choose whichever measure achieves the better result. In this case, the Court of Appeal considered and gave some helpful guidance in relation to these different measures...more
   
May 2016 Whether industry standard terms were ‘standard terms of business’ under UCTA
AFRICAN EXPORT-IMPORT BANK v SHEBAH EXPLORATION
The Court considered whether some industry standard terms used by a bank were its ‘written standard terms of business’ for the purposes of the Unfair Contract Terms Act 1977...more
   
May 2016 'Term Sheet' found legally binding
NEW MEDIA HOLDING COMPANY v KUZNETSOV
A Term Sheet, which set out some terms in relation to the control of a company, was found to be legally binding...more
   
May 2016 Relevance of words deleted from a draft contract
NARANDAS v BRADSTOCK (CA)
The question for the Court of Appeal here was whether wording deleted from a contract during the course of the drafting and negotiation process could be taken into account to interpret the final form of the agreement in order to resolve an ambiguity in the words which remained...more
   
May 2016 Scope of 'reasaonble endeavours' obligation
BRISTOL ROVERS FOOTBALL CLUB v SAINSBURY’S (CA)
The Court of Appeal considered the scope of an express duty of good faith in the context of the parties’ respective obligations under a contract to sell a football stadium and the extent of a reasonable endeavours obligation to obtain planning permission acceptable to the purchaser...more
   
March 2016 Standard terms, time limits and UCTA
COMMERCIAL MANAGEMENT v MITCHELL DESIGN
The Court decided that a term proposed in a sub-contractor's standard terms and conditions, which introduced a time limit for claims, had not been included in the final sub-contract. It also concluded that if it had been incorporated, it would not have satisfied the reasonableness test under UCTA and so would have been unenforceable...more
   
March 2016 Termination of outsourcing contract upheld
BT CORNWALL v CORNWALL COUNCIL
A Council’s action to terminate a long-term outsourcing contract with its supplier after only two years due to to the supplier’s failure to meet key performance indicators was upheld. The supplier’s attempt to get an injunction to prevent termination was unsuccessful…more
   
March 2016 Beware ‘collateral contract’ varying agreement terms
HUGHES v PENDRAGON (CA)/C&S v ENTERPRISE INSURANCE
The Hughes case involved a collateral contract which sidestepped a provision in the seller's terms and conditions which said that no amendment to the sale contract was effective unless signed by the seller. Although there were no details agreed regarding the exact price, specification or delivery date, a contract was still found to exist…more
   
March 2016 Liability for data security breaches
SILVERPOP SYSTEMS v LEADING MARKET TECHNOLOGIES
This is a US case in which a provider of digital marketing services was found not to be liable for an alleged breach of a service contract’s confidentiality provision when it suffered a data breach exposing a customer’s e-mail list. This decision has enormous potential ramifications unless it is overturned on further appeal…more
   
January 2016 General Data Protection Regulation - Apportioning Security Risk
This article (which is featured by the Society of Computers and Law here) discusses the appropriateness of uncapped liabilities and indemnities for data security breaches and how the implementation of the new General Data Protection Regulation might make that debate even more important…more
   
January 2016 Revised guidance on when terms will be implied into contracts
MARKS AND SPENCER v BNP PARIBAS (SC)
The Supreme Court has ruled that a term can only be implied if it is so obvious as ‘to go without saying’ or if without it the contract would lack ‘commercial or practical coherence’. Also if the agreement is very detailed and has been negotiated by lawyers, the Courts are less likely to imply a term…more
   
January 2016 Limitation and exclusion clauses in a professional appointment
PERSIMMON HOMES v OVE ARUP
A limitation and exclusion clause in a professional appointment has been interpreted as protecting the consultant from liability relating to asbestos at a development site, even though the consultant was aware of the presence of asbestos from an early stage. Although this was a construction case, the Technology and Construction Court’s comments on the interpretation of the liability and exclusion clause have wider application to other types of commercial contracts…more
   
January 2016 Applying ‘business sense’ to interpretation of an indemnity
WOOD v SURETERM & CAPITA (CA)
In this decision the Court of Appeal has confirmed that the wording of an indemnity should be interpreted in accordance with its plain meaning, even if this makes the clause particularly uncommercial for one party…more
   
January 2016 How liability in both contract and tort is assessed
WELLESLEY PARTNERS v WITHERS (CA)
The Court of Appeal decided that where there is potential liability in both contract and in tort, the narrower contractual principle of ‘remoteness of loss’ will be applied. A firm of solicitors was sued for professional negligence after wrongly drafting a partnership agreement which potentially caused its client significant losses…more
   
December 2015 Test for 'penalty' clauses reviewed
CAVENDISH SQUARE HOLDING v EL MAKDESSI and PARKINGEYE  v BEAVIS (SC)
The Supreme Court has decided that the clauses challenged in the combined appeals of these two cases, which involved very different facts and financial sums, were not penalties and were consequently enforceable. In doing so, it questioned the ‘genuine pre-estimate of loss’ test previously used to determine whether a contractual provision is a penalty…more
   
December 2015 Interpretation of ‘exclusive remedy’ and exclusion clause
SCOTTISH POWER UK v BP EXPLORATION

This case involved the remedies available to a customer following a failure to supply gas. The Court had to interpret a compensation mechanism which was stated to be an ‘exclusive remedy’ for breach of the supply provision as well as the types of liability excluded in the exclusion clause…more
   
December 2015 Incorporation of terms from framework agreement
NORTHROP GRUMMAN v BAE SYSTEMS (CA)
In this decision the Court of Appeal found that a buyer was entitled to end a software licence without reason due to a termination clause in a framework agreement whose terms were incorporated into the licence…more
   
December 2015 Misrepresentation and loss of remedies
SALT v STRATSTONE SPECIALIST (CA)
The Court of Appeal has clarified that a Court can only award compensation for an ‘innocent misrepresentation’ (under the Misrepresentation Act 1967) as an alternative remedy to having the contract set aside where the right to have the contract set aside has not been lost…more
   
October 2015 Interpretation of clause disastrous for one party
ARNOLD v BRITTON (SC)
This was a dispute over the interpretation of a service charge provision. The main issue was whether the language used in the contract reflected what the parties intended to say. The Courts will not override clear wording when determining the parties’ intentions, even though applying that principle here was disastrous for the tenants…more
   
October 2015 ‘Double’ or ‘qualified’ contractual obligations – which?
MT HØJGAARD v E.ON CLIMATE AND ROBIN RIGG (CA)
Typically contracts contain a multitude of contractual warranties and obligations. Often these are included by the purchaser/customer on the ‘kitchen sink’ principle but, as this case demonstrated, that may not always have the effect that was intended. A dispute arose over the standards of performance required and the nature of warranties contained within several documents which together formed a construction contract…more
   
October 2015 Duty to act with ‘honesty and integrity’ implied
D&G CARS v ESSEX POLICE AUTHORITY
There have been a number of decisions in 2015 where the Courts were asked to decide whether a general duty of good faith should be implied into a contract. The Courts have also been asked to consider the impact of various express contractual provisions along similar lines. Here,it was confirmed that a general duty to act with ‘honesty and integrity’ should be implied but other cases which we have also reviewed have resulted in a different outcome: Portsmouth City Council v Ensign Highways, Myers v Kestrel and Greenclose v National Westminster Bankmore
   
October 2015 Importance of formalities for signing contracts with overseas companies
INTEGRAL PETROLEUM v SCU-FINANZ (CA)
The Court of Appeal ruled that a contract between two Swiss companies and governed by English law was not binding as it was not signed by two authorised representatives on behalf of one of the companies, as required under the laws of Switzerland…more
   
October 2015 European Court ruling that 'Safe Harbor' is invalid
The European Court declared on 6th October 2015 that the 'Safe Harbor' scheme that governs the transfer of European data to the US is invalid, effective immediately. This decision will affect businesses who transfer EU data to US companies which are certified under the Safe Harbor scheme, including companies that outsource data processing of EU data to the States, who may now need to revisit their data security measures…more
   
July 2015 Liability provisions found unreasonable under UCTA
SAINT GOBAIN BUILDING DISTRIBUTION (T/A INTERNATIONAL DECORATIVE SURFACES) v HILLMEAD
Certain liability provisions in a supplier’s standard terms and conditions have been found to be unreasonable under UCTA. This was the case even though the buyer had a remedy of a replacement of the defective goods or could claim financial compensation up to the invoice value of the goods…more
   
July 2015 Neither party won ‘battle of the forms’
TRANSFORMERS & RECTIFIERS v NEEDS
This case involved the so-called ‘battle of the forms’ in relation to which terms applied to some contracts. A dispute arose following a long course of dealing: one party said that its terms were applicable because they were printed on the back of its purchase orders; the other party submitted that its terms applied as they were referred to on its acknowledgements of order and that any liability for breach of contract on its part was limited or excluded by those terms and conditions…more
   
July 2015 Liquidated damages cannot be claimed indefinitely
MSC MEDITERRANEAN SHIPPING v COTTONEX ANSTALT
This decision considered how long a party could claim liquidated damages following a serious breach of contract rather than choosing to end the contract and claim its actual loss as damages…more
   
July 2015 Sales 'recommendation' affected licence terms
AFD SOFTWARE v DCML
A software licensing dispute highlighted the dangers of representations made by staff during the sales process and their effect on the licence terms which were subsequently accepted by the customer…more
   
March 2015 Exchange of emails created binding settlement
BIEBER v TEATHERS
An exchange of emails between the parties' lawyers was held to constitute a binding settlement without any further detailed agreement being required…more
   
March 2015 Liquidated damages clause held to be unenforceable penalty
UNAOIL v LEIGHTON OFFSHORE
The Court held that a liquidated damages clause requiring a contractor to pay its sub-contractor US$40 million in the context of a sub-contract worth US$55 million was an unenforceable penalty…more
   
March 2015 ‘Friendly discussions’ requirement in dispute clause enforceable
EMIRATES TRADING AGENCY v PRIME MINERAL EXPORTS
This case involved a dispute resolution clause which required the parties to seek to initially resolve a dispute by ‘friendly discussions’. The Court had to decide how this clause should be interpreted, whether the provision was enforceable and if so, whether the clause been complied with…more
   
March 2015 Interpretation of time limit for warranty claim
THE HUT GROUP v COOKSON
Here the interpretation of a clause imposing a time limit for serving notice of a breach of a warranty claim was critical to whether the buyer had an actionable claim. The question was whether time starts to run when the party becomes aware of factual grounds that may amount to a claim, or only at the point at which the buyer knows there is a proper basis for bringing a claim…more
   
January 2015 Loss of profit - direct or indirect loss
POLYPEARL v E.ON ENERGY SOLUTIONS
In this case it was confirmed that loss of profits can be a direct loss. The Court assumed that a direct loss of profits was not intended to fall within an exclusion of ‘indirect and consequential loss’...more
   
January 2015 Termination for convenience clause limited claim for loss of profit
COMAU UK v LOTUS LIGHTWEIGHT STRUCTURES
The Court considered whether there had been a correct termination when a breach occurred and also whether a party’s claim for loss of profit following a termination for default could be affected by a termination for convenience provision...more
   
January 2015 Duty of good faith not implied in agency agreement
ACER INVESTMENT MANAGEMENT v MANSION GROUP
This case involved the question of whether a duty of good faith should be implied into a non-exclusive agency agreement.  On the face of it an agency type agreement ought to be a prime candidate for a duty of good faith but in this particular case the Court said the answer was ‘no’...more
   
September 2014 Liability where beneficiary under an indemnity is itself at fault
GREENWICH MILLENNIUM v ESSEX SERVICES GROUP (CA)
A sub-contractor was held liable under an indemnity agreed with its immediate superior contractor in respect of claims by parties higher up the contractual chain even though the immediate superior contractor had failed to detect the defective workmanship which resulted in the claims...more
   
September 2014 Conditions for claiming under an indemnity
HERITAGE OIL v TULLOW (CA)
This case looked at whether a buyer's strict compliance with a contractual notice provision had to be met in order for the buyer to be able to exercise its right to an indemnity from the seller under the terms of the agreement...more
   
September 2014 Duty of good faith implied in ‘relational’ contract
BRISTOL GROUNDSCHOOL v INTELLIGENT DATA CAPTURE
The Court ruled on a claim concerning a contractual relationship involving the supply and ongoing updating of online training materials under which one of the parties alleged there had been a breach of an implied duty of good faith...more
   
September 2014 Implication of terms into a contract
MARKS AND SPENCER v BNP PARIBAS (CA)
The Court of Appeal decided that if a party wishes to claim that there is an implied term in a contract, that party must show that: (a) the term is part of the agreement (even though not expressly written); and (b) it is necessary to achieve the parties’ common objective in entering into the agreement. It is not sufficient simply to show that the term could or should be part of the agreement...more
   
June 2014 Excluding liability and fiduciary/good faith duties
FUJITSU SERVICES v IBM UNITED KINGDOM
In a dispute over a partnering sub-contract, it was considered whether liability for loss of profit was effectively excluded and whether a fiduciary duty as well as a duty of good faith existed in an IT services sub-contract...more
   
June 2014 Termination notice deemed invalid
FRIENDS LIFE v SIEMENS HEARING INSTRUMENTS (CA)
A termination notice was deemed invalid because it was not given strictly in accordance with the exact terms specified in the agreement. This decision shows it is necessary to adhere very precisely to all the requirements of a termination clause to avoid or minimise the risk of a termination notice being held ineffective...more
   
June 2014 Importance of terminating with care
VIVERGO FUELS v REDHALL ENGINEERING SOLUTIONS
This case demonstrated the importance of terminating a contract with care. If a party does not have, or no longer has, the right to terminate or if it does not exercise its rights properly then this can mean that an ‘innocent’ party is itself in breach which then gives the party originally in breach a right to terminate instead. Here, the Technology and Construction Court decided that a customer was in breach when it wrongfully tried to terminate an agreement because the alleged breach of contract no longer existed at the time the termination notice was sent...more
   
June 2014 Abuse of a dominant position via licence terms
The UK Office of Fair Trading has been investigating alleged anti-competitive behaviour by a software supplier in relation to restrictive contractual provisions imposed within its software licences...more
   
April 2014 Liability for misrepresentations made to a third party
CRAMASO v OGILVIE-GRANT, EARL OF SEAFIELD & OTHERS (SC)
The highest Court in the United Kingdom, the Supreme Court, considered whether a party could be liable for a negligent misrepresentation made before a contract was entered into where the party to which the representation was originally made was not the ultimate contracting party...more
   
April 2014 Injunction granted to stop wrongful termination where limitation renders damages an inadequate remedy
AB v CD (CA)
This case looked at the situation where one party sought an urgent interim injunction to stop the other from wrongfully terminating a contract in circumstances where an exclusion clause would seemingly have prevented the recovery of substantial damages arising from the termination. It is established law that such an injunction will not be granted if damages would be an adequate remedy for the wrongful termination. But how does that apply in cases of an alleged breach of contract where there is a provision limiting the recoverable damages to a level below what might be suffered and which, but for the limitation might be claimable?...more
   
April 2014 Liability arising out of ‘one event’
AIOI NISSAY v HERALDGLEN
This decision looked at the issue of whether the attack on the Twin Towers of the World Trade Center amounted to two ‘events’ or one for the purpose of applying the liability limits in various insurance policies...more
   
April 2014 Claim for unpaid deposit on termination
FIRODI SHIPPING v GRIFFON SHIPPING (CA)
The question of whether a seller’s claim for non-payment of a ‘deposit’ by a buyer was limited to compensation for its actual losses or whether it was entitled to claim the deposit agreed in full was the focus of this case. It was highlighted that the main purpose of a deposit is to encourage a buyer to perform and it was confirmed that a right to a deposit which had accrued before termination of the agreement was not lost due to the termination...more
   
January 2014 Contract formed through exchange of emails
PROTON ENERGY v ORLEN
This case does not make new law but it is a reminder that contracts can be formed in ways other than the execution of a formal written contract. The Court considered whether a binding contract had been concluded between the parties, based on a review of their negotiations which was largely through an exchange of emails. It found that there was a binding agreement as, even though not all of the terms had been finalised, the parties had agreed on all of the essential terms...more
   
January 2014 No copyright in functionality of computer program confirmed
SAS INSTITUTE v WORLD PROGRAMMING (CA)
The Court of Appeal has confirmed that copyright in a computer program does not protect its programming language or its functionality from being reproduced. This decision reiterates that it will be difficult to establish copyright infringement in software programs without evidence of copying of the underlying source code. The key issues in question were (1) the extent to which the developer of a computer program may lawfully replicate the functions of an existing computer program; and (2) the materials that he may lawfully use for that purpose...more
   
January 2014 Early termination payment not a penalty
BERG v BLACKBURN ROVERS FC
The High Court has confirmed that the law on penalties only applies where the trigger for payment is a breach of contract and not where an agreed sum was payable as compensation on the exercise of an early termination right in a fixed term contract...more
   
January 2014 Duty to act reasonably in mitigating losses not onerous
MANTON HIRE v ASH MANOR CHEESE (CA)

Here, the Court of Appeal considered whether a customer under a hire agreement for a fork lift truck had failed to mitigate its losses, by refusing to accept an unclear proposal made by the supplier to remedy a fundamental problem with the original truck supplied. All contracting parties are under an implied obligation to take reasonable steps to mitigate their loss where they are the victims of a breach of contract. In commercial B2B contracts this will often take the form of accepting a reasonable offer from the party in default offering to take steps to rectify the breach...more
   
November 2013 Exclusion clause and cap on liability deemed reasonable under UCTA
ELVANITE v AMEC
An exclusion clause and a limit on liability were found to be reasonable under UCTA (the Unfair Contract Terms Act) and a clause allowing a party only one year to make a claim was held to be effective...more
   
November 2013 Term of implied licence to use software
NOEMALIFE v INFINITT
The Court was asked to consider whether an implied royalty-free licence granted in relation to software which was used for the purposes of a services agreement, automatically continued after the agreement's initial period when it was extended...more
   
November 2013 Will an overall cap on liability always work?
SABIC UK PETROCHEMICALS v PUNJ (Part 1)
The Technology and Construction Court has made a perhaps unexpected decision in interpreting a broad and relatively standard ‘catch all’ limit of liability clause that sought to protect a supplier. The Court said the aggregate liability clause only applied to claims for breaches of contract or so called tortious liabilities such as negligence. This case could perhaps provide a clue to answer the question of whether contractual indemnities take precedence over general limitation clauses...more
   
November 2013 Do payments under performance bonds/guarantees count against caps on liability?
SABIC UK PETROCHEMICALS v PUNJ (Part 2)
In addition to the issues set out in Part 1 of the SABIC case, the Court had to consider whether payments made under a performance bond and a guarantee would count against a supplier’s limit on liability...more
   
November 2013 Agreement to agree can be enforceable
MRI v ERDENET (CA)
In this case an ‘agreement to agree’ in respect of certain charges and a delivery schedule in a contract for the sale of copper concentrates was found to be enforceable even though traditionally such an arrangement would be thought to be unenforceable for lack of certainty...more
   
November 2013 The dangers of retention of title clauses
CATERPILLAR (WILSON) v HOLT (CA)
The Court of Appeal had to consider a retention of title clause which was used as part of an agreement to supply finished goods for immediate resale. The case showed that the use of such a clause can have a major drawback because it was said that the operation of the clause was inherently inconsistent with the nature of the trading relationship between the parties, a situation which has previously caused the Courts problems...more
   
September 2013 Was a breach serious enough to justify termination?
TELFORD HOMES v AMUPURIUS NU HOMES (CA)
A delay of several months in delivering a commercial development due to funding difficulties did not amount to a breach serious enough to justify termination of the contract in the context of the project as a whole...more
   
September 2013 Express duty of good faith does not extend to termination
TSG v SOUTH ANGLIA
The Court was asked whether a contractual right to terminate for convenience had to be exercised in good faith and whether there was an implied term to this effect. The answer to both of these was ‘no’. It seems the Courts are likely to interpret express contractual obligations of good faith narrowly and will hesitate before implying such obligations...more
   
September 2013 Acting diligently and all reasonable endeavours
MORRIS HOMES v KEAYS
Obligations to ‘act diligently’ in carrying out works and to use ‘reasonable endeavours’ to complete are quite common in commercial agreements. In this case the Court considered whether there was an overlap between these two contractual requirements...more
   
September 2013 Did a 'priority of documents' clause apply?
RWE v BENTLEY
The Court held that it did not need to look at a ‘priority of documents’ clause because it only applied where there was an ambiguity or discrepancy that remained once the Court had interpreted the contract in the usual way...more
   
May 2013 Reasonably foreseeable loss
JOHN GRIMES v GUBBINS (CA)
The Court of Appeal was asked to review the law governing the damages which can be recovered for breach of contract and when damages will be regarded as being ‘too remote’ to be recoverable. As a general rule, once damages of a particular kind are held to be ‘reasonably foreseeable’ in the sense of being ‘not unlikely to result from a breach’, then they can be claimed irrespective of the extent of the damage suffered...more
   
May 2013 Is there an implied duty of 'good faith'?
YAM SENG v INTERNATIONAL TRADE CORPORATION

An overriding contractual duty of ‘good faith’ is a concept imposed by law in many continental European jurisdictions but not one which is generally implied under English law (at least not in those terms). In this decision the Court implied two specific obligations into a distribution agreement, portraying them as aspects of good faith...more
   
May 2013 Express obligation of 'good faith'
MID ESSEX HOSPITAL NHS TRUST v COMPASS GROUP (T/A MEDIREST) (CA)

This decision looked at an express obligation to act in 'good faith' set out in the written contract. The Court of Appeal overturned the High Court’s earlier ruling by giving a much narrower interpretation to the words that the parties had signed up to...more
   
May 2013 No implied term unless all reasonable people agree
DEAR v JACKSON (CA)

The Court of Appeal overturned the High Court’s decision and looked at the different approaches that have previously been taken in relation to the test for implying terms into a contract. The Court of Appeal seemed to take a more restrictive approach to the implication of terms...more
   
February 2013 Documents required to be disclosed under audit clause
TRANSPORT FOR GREATER MANCHESTER v THALES

The Court considered the extent to which a supplier must disclose information pursuant to an audit clause under a contract for the supply of goods and services...more
   
February 2013 Exclusion clause interpreted narrowly
KUDOS v MANCHESTER CENTRAL CONVENTION COMPLEX (CA)

A clause which expressly excluded a customer’s liability for loss of profits did not apply where the customer had prematurely terminated and refused to allow continued performance of the contract. The Court of Appeal applied what it saw as ‘business common sense’ notwithstanding an apparently clear exclusion clause...more
   
February 2013 Warranties v Representations
SYCAMORE BIDCO v BRESLIN

In this case, the Court considered whether express warranties in a share purchase agreement could also amount to representations (statements made before a contract on which a party relies when entering into a contract). This issue arose as a much larger sum was available in damages if there had been a misrepresentation as opposed to a simple breach of contract and so the purchaser claimed that the warranty given was also a representation...more
   
February 2013 Standard of reasonableness required for withholding consent
BARCLAYS v UNICREDIT

The Court applied an objective standard of reasonableness in deciding whether consent to the early termination of certain finance transactions had been reasonably withheld by one of the contracting parties...more
   
February 2013 Term Sheet could not be used to imply terms into signed contract
SNCB v UBS

This decision involved the interpretation of certain finance contracts and, in particular, the relevance of a ‘Term Sheet’ which was previously agreed between the parties to document the agreed outline commercial terms. The case also looked at the basis upon which terms can be implied into a written contract...more
   
February 2013 Implied terms and exercising discretion to act in ‘good faith’
YILPORT v BUXCLIFF

The Court was asked to look at implied terms and the restrictions on the exercise of contractual discretion specifically in relation to the contract charges. In some ways this is an interesting contrast to the decision in the SNCB v UBS case which dealt with similar issues...more
   
December 2012 Meaning of an assignment of intellectual property rights
WILKINSON v LONDON STRATEGIC HEALTH AUTHORITY
Contracts for the development or customisation of software, for the production of training materials or the creation of a consultancy report often have to attempt to resolve the typical struggle regarding the ownership of the resulting intellectual property rights between the customer and the supplier or consultant. Problems arise because, as the saying goes, very little, if anything, is completely original and this case addressed what was covered by an assignment of IPRs...more
   
December 2012 Enforceability of 'take or pay' commitments
E-NIK v DEPARTMENT FOR LOCAL GOVERNMENT
As in this case, commercial contracts often contain a commitment by the customer to purchase on a ‘take or pay’ basis ie to buy a minimum quantity of goods and/or services within a defined period. When those commitments are not complied with, questions then arise as to what the supplier’s entitlement is and the extent to which the supplier is under an obligation to mitigate its loss...more
   
December 2012 All inclusive 'full and final' settlement
POINT WEST v MIRVAN
A 'full and final' settlement was held to include issues not identified or formulated at the time the parties agreed the settlement so when reaching and documenting a settlement regarding a contractual dispute, it is necessary to be extremely careful to document exactly what is meant to be covered. It needs to be clear whether it is intended to be truly all encompassing or should purely relate to those defects, breaches or liabilities known of at the time the settlement is agreed...more
   
December 2012 Exclusion of set-off rights
WILSON v HOLT
In this case the Court had to decide whether the exclusion of a right of set-off in a contract satisfied the UCTA reasonableness test and whether it had been properly incorporated into the contract...more
   
October 2012 Letters of Intent and limits of liability
AMPLEFORTH v TURNER & TOWNSEND
This case has interesting implications for contracting parties and their advisors and covers issues such as the appropriate use of Letters of Intent where projects have to be started early before formal contracts have been concluded and the enforceability of limitations of liability...more
   
October 2012 Does an indemnity cover future losses?
K/S PRESTON STREET v SANTANDER
The scope of an indemnity was the issue in this case and, in particular, whether it extended to cover future losses. Indemnities have traditionally been most common in relation to the risk of third party intellectual property infringement claims where the supplier agrees to indemnify the customer against any damage it may suffer from using a particular deliverable should it infringe. However, indemnities in respect of other risks/losses are becoming more common...more
   
October 2012 Extent and enforceability of ‘limited warranty'
CHRISTIE’S v AVRORA
This decision concerned an attempt by the well-known auction house to ensure that any remedies of the buyer of a painting were limited to claims for breach of contract under an express ‘Limited Warranty’...more
   
October 2012 Incorporation of standard terms
ALLEN FABRICATIONS v ASD
Businesses should be reminded that they should be consistent in the way in which they incorporate their standard terms, such as making sure that they are printed on the back of, or referred to in all, proposals. One of the key issues considered in this case was whether a limitation of liability clause had been effectively incorporated as part of the supplier’s standard terms...more
   
September 2012 Resale of downloaded software permitted in EU in certain circumstances
USEDSOFT v ORACLE
The European Court of Justice ruled that perpetual software licences granted for a single up-front payment are treated as ‘sales’. This means licensees can now transfer the right to use the software to a third party despite any express contractual provisions to the contrary. There are several important ramifications for software owners whilst it possibly opens up opportunities for licensees...more
   
September 2012 Using reasonable endeavours and due diligence
AMPURIUS NU HOMES v TELFORD HOMES
This case looked at the meaning of a commitment to carry out contractual obligations with ‘reasonable endeavours’ and ‘due diligence’, terms often used in many contracts. The Court gave some useful guidance on how these commitments are interpreted and whether the financial resources of the party giving the obligation should be considered...more
   
September 2012 Cookies - getting the recipe right
Given that virtually every website and many marketing e-mails use cookies, it is important for all organisations to note that the law has changed regarding the use of cookies - it is no longer enough simply to tell website users/recipients about cookies and allow them to opt out. There is now a requirement to obtain consent to the use of cookies and similar technologies on websites and as part of marketing activities...more
   
May 2012 Endeavours clauses remain inherently uncertain
BLACKPOOL AIRPORT v JET2.COM (CA)
The Court of Appeal has confirmed the High Court’s earlier ruling in this case on the meaning of ‘all reasonable endeavours’, rejecting the Airport’s argument that such an obligation did not require it to act against its own commercial interests. The CA also looked at the enforceability of an ‘endeavours’ provision. However, the decision leaves a tremendous amount of uncertainty and is, in many respects, very unsatisfactory...more
   
May 2012 No copyright in functionality or programming language of computer program
SAS INSTITUTE v WORLD PROGRAMMING
This case came before the High Court in 2010 and revisited the issue of whether producing the same functionality of another’s software by using independently developed code would amount to copyright infringement as opposed to recreating that functionality by directly copying the source code of that software without consent. The European Court of Justice has now confirmed that there is no copyright in the functionality, programming language or format of data files of a computer program...more
   
May 2012 Side letter confirmed as non-binding agreement to agree
MOUNTWEST 838 v BACKMUIR TRADING
Some useful help was provided in this decision on when a breach of contract is considered material, whether that breach is capable of remedy and what is required for a notice to terminate a contract to be effective...more
   
May 2012 Termination for material breach
BARBUDEV v EUROCOM CABLE MANAGEMENT BULGARIA (CA)
This is an appeal of an earlier decision and the Court of Appeal confirmed that a side letter was a non-binding agreement to agree but, contrary to the High Court Judge, found that the letter did show an intention to create legal relations, which is one of the necessary elements for a contract to be formed...more
   
April 2012 Cancellation vs termination for serious breach
JONES v TATE (CA)
The distinction was discussed between the right: (1) to have a contract set aside from the outset so that the parties are put back into the position they were in before the contract was made; and (2) to terminate a contract for serious breach, which simply brings the contract to an end in terms of future obligations...more
   
April 2012 Right to cancel a contract in practice
ERLSON PRECISION HOLDINGS v HAMPSON
Here the Court decided on the right to cancel (or rescind) a contract from the outset, in which it was demonstrated that this right can apply where a change in circumstances has been dishonestly concealed, which was important in the context of the contract in question. It showed the dangers of deliberately withholding information and how a company can be found liable for its employees’ acts and omissions...more
   
April 2012 Duty of good faith in long-term contracts
COMPASS GROUP (T/A MEDIREST) v MID ESSEX HOSPITAL NHS TRUST
This case shed light on how important a contractual obligation to co-operate in ‘good faith’ can be. A duty of ‘good faith’ is a concept imposed in many continental European jurisdictions but which is poorly defined in English law and has been comparatively rare in commercial contracts...more
   
February 2012 Approach to the interpretation of clauses with two possible meanings – common sense prevails
RAINY SKY v KOOKMIN BANK (SC)
The Supreme Court has confirmed that the Court will look to adopt a commercial approach when there are ambiguities in commercial contracts...more
   
February 2012 Correcting contracts for mistake
DAVENTRY DISTRICT COUNCIL v DAVENTRY & DISTRICT HOUSING (CA)
The Court of Appeal ordered an outsourcing contract to be corrected where one party took advantage of the other’s failure to appreciate the meaning of one of the terms, even though the meaning from the drafting appears to have been pretty clear...more
   
February 2012 What exactly does ‘consent not to be unreasonably withheld’ mean?
PORTON CAPITAL v 3M
This case revealed some interesting comments from the High Court when determining whether a party to a contract has withheld consent reasonably or not...more
   
December 2011 Claim under indemnity challenged
RUST CONSULTING v PB
This case demonstrates that just because you have the benefit of an indemnity from a third party, you cannot act without considering the interests of the indemnifying party…more
   
December 2011 Not following termination procedure put innocent party in breach
GESNER v BOMBARDIER (CA)
A buyer who terminated for late performance without following the correct contractual termination procedure to the letter was itself found to be in breach…more
   
December 2011 Liquidated damages – a penalty or not?
AZIMUT-BENETTI v HEALEY
The test for determining when a liquidated damages provision constitutes a ‘penalty’ and hence when it is unenforceable was considered in this case. The Court adopted a ‘commercial justification test’ and viewed the clause in question as seeking to strike a balance between the commercial interests of the parties…more
   
December 2011 Meaning of ‘during this agreement'
INTERACTIVE INVESTOR v CITY INDEX (CA)
The term of a contract needs to be one of the most straight-forward provisions in an agreement. However, this decision shows there can be major problems if the provisions and terminology used regarding the overall duration of an agreement, the termination notice period and any exit assistance period are not thought through properly and drafted clearly and consistently…more
   
September 2011 All reasonable endeavours – obligations not limited by commercial interests
JET2.COM v BLACKPOOL AIRPORT
The High Court was asked to consider whether an obligation to use ‘all reasonable endeavours’ required a party to act against its own commercial interests. In this case, the answer was ‘yes’…more
   
September 2011 Right of first refusal or simply opportunity to negotiate?
ASTRAZENECA UK v ALBEMARLE INTERNATIONAL (Part 1)
This decision looked at when an exclusion clause applies to a deliberate breach of contract and demonstrates that great care is required when drafting and agreeing a ‘right of first refusal’…more
   
September 2011 Application of loss of profit exclusion
ASTRAZENECA UK v ALBEMARLE INTERNATIONAL (Part 2)
In addition to the issues set out in Part 1 of the Albemarle case, the High Court had to consider whether the effect of an exclusion of liability for loss of profit would be to deprive one party of any substantial remedy for its real loss…more
   
September 2011 Side letter not legally binding despite need for good faith
BARBUDEV v EUROCOM CABLE MANAGEMENT BULGARIA
Side letters are often signed in commercial transactions, sometimes when circumstances do not permit all the terms agreed to be incorporated into the formal contract. This case has highlighted that care must be taken to ensure that if a side letter is made with the intention to create a legally binding agreement, its terms must be sufficiently certain so that it is not treated as an unenforceable ‘agreement to agree’...more
   
July 2011 Gross negligence – an English concept?
CAMARATA PROPERTY v CREDIT SUISSE SECURITIES
The meaning of ‘gross negligence’ was considered and whether it is a recognised concept in English law separate from simple negligence. The distinction is important since some civil law systems, such as in continental Europe, do not allow a party to exclude or limit its liability for gross negligence, whereas in England this is possible...more
   
July 2011 Delay, extensions of time and the prevention principle
ADYARD ABU DHABI v SDS MARINE SERVICES
This was a construction case in which the issue was whether a party could cancel certain shipbuilding contracts and reclaim sums it had already paid where there had been a delay in completing the ships.  Amongst other things, the Court addressed in what circumstances the shipbuilder was entitled to an extension of time where the customer had requested changes to the design, particularly given the fact that there was a contractually agreed mechanism for the shipbuilder to request an extension...more
   
July 2011 Outright prohibition on selling via the internet deemed anti-competitive
On 3 March 2011, the Advocate General, legal advisor to the European Court of Justice, delivered an opinion in a case concerning Pierre Fabre, a French company which had absolutely prohibited its selected distributors from making sales over the internet. The case followed the introduction of the revised Vertical Agreements Block Exemption Regulation in 2010 which prohibit such outright bans...more
   
May 2011 Sale of Goods Act and implied terms not applicable to software supply contract
LONDON BOROUGH OF SOUTHWARK v IBM UK
LBS was unsuccessful in its claim that I had breached a contract to supply third party software because the software was, allegedly, of unsatisfactory quality and/or was unfit for purpose. The decision looks at several specific issues: the construction of an express warranty as to satisfactory quality in the light of other contractual terms, whether the Sale of Goods Act 1979 applied to a software licence and whether the Unfair Contract Terms Act 1977 applied to the exclusion of implied terms...more
   
May 2011 Entire agreement clauses under spotlight again
AXA SUN LIFE SERVICES v CAMPBELL MARTIN & OTHERS (CA) Part 1
This dispute related to whether an entire agreement clause was effective to exclude claims for misrepresentation, breach of collateral warranties (effectively ‘side promises’) and/or implied terms and the application of the Unfair Contract Terms Act 1977 to the entire agreement clause. Similar cases have been before the High Court recently but seemingly this was the first time these issues had come before the more authoritative Court of Appeal...more
   
May 2011 One-sided set-off and conclusive evidence clauses
AXA SUN LIFE SERVICES v CAMPBELL MARTIN & OTHERS (CA) Part 2
As well as issues relating to entire agreement clauses (see Axa v Campbell Part 1), this case also demonstrated that care is required when drafting unilateral set-off clauses and so called ‘conclusive evidence’ clauses in agreements containing standard terms as both may be subject to the reasonableness test under the Unfair Contract Terms Act 1977...more
   
May 2011 Enforceability of unilateral clause to increase fees
AMBERLEY v WEST SUSSEX COUNTY COUNCIL (CA)
This case illustrated that where a party is seeking to rely on a unilateral right to increase its fees, very clear and precise drafting will be required to achieve that. A right to ‘review’ does not amount to a right to unilaterally increase!...more
   
May 2011 English and Scottish law to diverge?
The law of contract in Scotland has long been independent from the law in England albeit that the differences are somewhat limited. However, the differences may be about to increase. The Scottish Law Commission has issued a discussion paper as part of its review of the law of contract. This paper focuses on how contracts are interpreted by the Courts and what evidence they take into account. It has been prompted by the developments taking place in the European Union, where proposals are currently being considered regarding various options which might be pursued with the objective of harmonising contract law throughout Europe...more
   
March 2011 Refusing to perform may repudiate the contract
DE BEERS v ATOS ORIGIN
Those involved in contracts for IT services will be interested in this case because it deals with some of the key issues relating to the scope and management of IT contracts and termination. It illustrates how a complex software development contract can go wrong and how the supplier was held liable for damages for breach of the agreement by suspending work...more
   
March 2011 Losses held not indirect
McCAIN FOODS v ECO-TEC
Many suppliers have a false conception regarding the extent to which they are covered by an exclusion of ’indirect or consequential loss’ which seeks to limit their exposure if there are problems with performing a contract. This decision illustrates some of the pitfalls of such wording, which did not reduce the damages at all because the losses claimed were held to be ‘direct’...more
   
March 2011 Industry-standard exclusions reasonable under UCTA
RÖHLIG (UK) v ROCK UNIQUE (CA)
Certain standard trading terms excluding various rights have been held reasonable under the Unfair Contract Terms Act 1977 (UCTA) and were therefore enforceable by a supplier...more
   
March 2011 When is there a contract?
IMMINGHAM STORAGE v CLARE (CA)
In this case, it was decided that a contract had been made between the parties when a signed quotation was accepted and that the wording “a formal contract will follow” did not make the agreement subject to contract...more
   
December 2010 Contractor ‘benefits’ from mistake in sub-contractor’s tender at its cost
TRADITIONAL STRUCTURES v HW CONSTRUCTION
This case concerned a sub-contractor who made a critical mistake when submitting a tender. In this era of modern technology where bid documents are often copied from previous documents, mistakes can easily be made. When that happens the courts will sometimes have to consider the position of the two contracting parties...more
   
December 2010 How long should you wait before terminating?
FORCE INDIA v ETIHAD AIRWAYS (CA)
A contracting party faced with serious breaches by the other side faces a difficult choice. Act prematurely and you risk purporting to terminate when you do not have the right to do so. You then lay yourself open to a claim for breach of contract and damages, not to mention ruining any possibility of a negotiated settlement and potentially allowing the party initially in breach to escape from its ongoing contractual commitments. Act too slowly and you risk having waived your rights even if the contract has the traditional waiver clause (whereby neither party waives the right to exercise its rights under the contract due to delay). This case looked at what a party must do in such circumstances...more
   
November 2010 Is copying software functionality an infringement?
SAS INSTITUTE v WORLD PROGRAMMING
In short, the answer is no. Or at least it seems to be under English law. This case revisited the issue of whether producing the same functionality of another’s software by using ‘independently’ developed code would amount to copyright infringement as opposed to recreating that functionality by directly copying the source code of that software without consent...more
   
November 2010 Unlimited liability if battle of the forms is lost?
GHSP v AB ELECTRONIC
This is another decision on the battle of the forms which highlights once again the dangers of starting work without fully agreeing terms. Here, the supplier failed to ensure the buyer had agreed to its terms and conditions and now faces unlimited liability against claims for its defective products...more
   
November 2010 Rectifying mistake possible despite entire agreement clause
SURGICRAFT v PARADIGM BIODEVICES
Generally, contracting parties cannot extricate themselves from a poorly drafted contract because they later have second thoughts. However, the Courts can assist where there is a genuine mistake in the agreement and to give effect to the intentions of the parties...more
   
November 2010 Retention of title clauses – how effective is yours?
ISHER FASHIONS UK v JET STAR RETAIL
This case suggested that a retention of title clause (often known as a ‘ROT’ clause) may not be effective if its operation is inconsistent with the overall trading relationship between the parties, such as where it appears in a contract for the supply of finished goods intended for immediate resale...more
   
November 2010 Care needed when amending definitions
ERICSSON v HUTCHISON 3G UK
Here is just a brief note on a recent case which emphasises the care required when amending definitions whilst varying a contract...more
   
September 2010 What types of damages are considered direct or indirect?
GB GAS HOLDINGS (CENTRICA) v ACCENTURE (CA)
This decision was an appeal against the High Court’s ruling that certain types of losses suffered by C were direct, including ex-gratia payments to customers, and were therefore not excluded by the liability clause set out in the contract. The question for the Court of Appeal was whether the range of direct losses claimed were indirect instead; if so, they would not therefore be recoverable...more
   
September 2010 Meaning of ‘all reasonable but commercially prudent’ endeavours
CPC v QATARI REAL ESTATE
The meaning of an ‘endeavours’ obligation in this case was examined as it involved a very untypical phrase obliging a party to use “all reasonable but commercially prudent” endeavours. It provided the Court with an opportunity to review and summarise the conclusions from other recent cases on this topic...more
   
September 2010 Economic climate excuse for contractual breach or termination?
3G GOLD GROUP v BDW and TANDRIN v AERO TOY STORE
Perhaps not surprisingly, the Courts have seen a number of cases in which contracting parties have sought to invoke the current economic difficulties as constituting force majeure and therefore excusing contractual breaches or even ‘frustrating’ a contract...more
   
September 2010 Self-help remedy of ‘set-off’ clarified
GELDOF METAALCONSTRUCTIE v CARVES (CA)
There has always been some doubt as to the extent to which claims under different contracts can be offset against one another. The Court of Appeal has sought to clarify the issue and has potentially extended the scope of the self-help remedy of equitable set-off...more
   
August 2010 Do not rely on terms being implied
DURHAM TEES VALLEY AIRPORT v BMI (CA)
This case emphasised the need for drafting to be explicit if a particular commitment is important rather than simply relying upon terms to be implied. Courts will not impose an obligation on a contracting party to ‘act reasonably’ when performing a contract...more
   
August 2010 Take care when terminating for non-payment
DOMINION v DEBENHAMS
Following the Shell case, it is clear that taking care when purporting to terminate for breach is very important. This was a case involving termination for non-payment and again underlines the risk of being too hasty...more
   
August 2010 Incorporation of contract terms
ROONEY v CSE BOURNEMOUTH (CA)
An aircraft maintenance company appealed against a decision that its standard conditions of trading were not incorporated into a work order form...more
   
August 2010 How far does the duty to mitigate go?
LOMBARD NORTH CENTRAL v AUTOMOBILE WORLD (CA)
An innocent party is generally under an obligation to take action to mitigate its loss in circumstances where the other contracting party is in breach of contract. This case provides some guidance on the extent of that duty...more
   
June 2010 Supplier's liability clause held unreasonable
KINGSWAY HALL HOTEL v RED SKY IT
A software supplier was held not to be able to rely on its limitation of liability clause and other clauses of its contract because of the way in which it had sold its products. Given that what the supplier did is not untypical, this decision may be very significant...more
   
June 2010 How not to terminate a contract
SHELL EGYPT WEST v DANA OIL EGYPT
This decision highlighted the importance of selecting and making clear in communications the right termination option when seeking to end a contract and provides a useful reminder of the choices to be made when thinking about terminating...more
   
June 2010 Replacing a sub-contractor in public contracts
WALL v CITY OF FRANKFURT
The European Court of Justice held that a change of sub-contractor (even if there is contractual provision for such a change) may, in exceptional cases, amount to a material amendment to the contract where the use of a particular sub-contractor was a critical factor in awarding the contract. In those circumstances, all necessary measures must be taken to restore the transparency of the procedure (possibly by way of a new award procedure)...more
   
June 2010 How to determine standard terms of business under UCTA
YUANDA (UK) CO v WW GEAR CONSTRUCTION
The Yuanda judgment set out some useful guidance on the Unfair Contract Terms Act 1977 (UCTA) and when the parties are to be regarded as having contracted on one party's standard written terms of business...more
   
April 2010 Need to revisit exclusion clauses
MARKERSTUDY v ENDSLEIGH
Liability clauses and the exclusions they contain are usually the most contentious terms in any commercial contract yet the parties are often still uncertain as to where liability will actually fall if there is a breach. This decision emphasises once again the need to be careful how exclusions are set out and to be crystal clear about which direct and indirect losses are excluded. But you thought your contract did that...more
   
April 2010 Contract or no contract?
RTS FLEXIBLE SYSTEMS v MÜLLER (SC)
Anyone negotiating commercial contracts will recognise the scenario where, because of the urgent need to get on with the project, work is allowed to start without there being a fully concluded agreement on all of the terms of the contract. In the absence of a signed agreement in this case, a contract was initially found to exist, then on appeal the court said there was no contract and now the Supreme Court has held a contract was indeed in place after all...more
   
April 2010 Contractual indemnity and duty to mitigate
CODEMASTERS v AUTOMOBILE CLUB DE L’OUEST
The Court was asked to interpret an indemnity in a licence agreement between a computer-game publisher and the organisers of the Le Mans race. Indemnities are worded in a variety of ways. They can range from wide-open coverage eg "all costs, losses, damages, expenses..." to more specific reference to the key areas of risk or to specific third party claims. Unless the contract provides otherwise, an indemnified party need not mitigate its loss...more
   
April 2010 Rewriting the rules on remoteness?
SYLVIA SHIPPING CO v PROGRESS BULK CARRIERS
This case looks at the potentially differing rules on assessing remoteness of damages that can be claimed for breach of contract. An appeal from an arbitration award was dismissed and damages associated with the delay in readiness of a vessel, which resulted in the cancellation of a sub-charter, were held to be foreseeable and hence could be claimed...more
   
February 2010 IT supplier found liable for fraud
BSKYB v EDS
The much awaited judgment in this high profile case has finally been delivered in favour of B with a possible award of at least £200m in damages. The High Court found an individual employee of E (now part of HP) had made a fraudulent misrepresentation...more
   
February 2010 Damages based on breaching party’s gain
PELL FRISCHMANN ENGINEERING v BOW VALLEY (PC)
This case was an appeal to the Privy Council (PC) from the Jersey Court of Appeal so it carries a significant degree of authority. It concerned the level of damages which might be awarded in exceptional cases where little or no direct financial loss has been suffered...more
   
February 2010 Letters of intent
WHITTLE MOVERS v HOLLYWOOD EXPRESS (CA)
Traditionally Courts bend over backwards to find a contract exists where the parties had begun performance whilst negotiations continued. However, in recent years the Court of Appeal has indicated a firm departure from that approach and this is once again reflected in this case...more
   
December 2009 Subject to contract’ may not always be effective
JIREHOUSE v BELLER
The significance of the words ‘subject to contract’, which are frequently used in correspondence and often stamped on drafts as a matter of course pending an agreed contract, was the main issue in this judgment. The words are meant to indicate the parties do not intend to be legally bound until an agreement is finally concluded, at which point these words are removed...more
   
December 2009 Application of English law to a US form contract
SEADRILL v GAZPROM
The High Court ruled that, despite a contract being derived from documentation originating from the US and using US terminology, the contract must be construed in accordance with English principles of contract law construction where the governing law of the contract is stated to be English law...more
   
November 2009 Broad liability exclusions and the dangers of terminating wrongly
LOBSTER PRESS v HEIDELBERG
This case highlighted several points of potential interest concerning the enforceability of contractual exclusions from, and limitations, upon liability. In particular, the decision featured warranty obligations limited to ‘repair or replacement’ and illustrated the danger of limitation and exclusion clauses that for different reasons could leave the other contracting party with little or no remedy...more
   
November 2009 Exclusion of set-off rights
KAUPTHING v MILL and PETROPLUS v SHELL
The High Court confirmed that parties can exclude all rights of set-off. ‘Set-off’ arises where a debtor has a form of counterclaim against a creditor, which is used to reduce or extinguish the creditor's claim...more
   
November 2009 Termination rights and refunding sums paid
GDYNIA v GEARBULK (CA)
The right to terminate a contract for breach is often one of the most valuable protections for any contracting party. It is therefore extremely important to be clear about the rights of termination - whether you are seeking to terminate or being faced with the threat of termination. Equally as key is understanding the consequences of termination...more
   
November 2009 When do changes to public contracts bring about new contract awards?
PRESSETEXT
A difficult question for public authorities is whether a contract initially tendered under the Public Contracts Regulations 2006 needs to be re-advertised where there are post-contract amendments reflecting changes in circumstances...more
   
September 2009 Negotiations and drafts inadmissible as evidence?
CHARTBROOK v PERSIMMON HOMES (HL)
This House of Lords case provided an important reminder of the need to ensure clear drafting of commercial contracts and of the primacy of the words used in the written contract. The so called ‘exclusionary rule’ that pre-contractual negotiations and drafts are inadmissible when interpreting a contract was confirmed...more
   
September 2009 Not notifying change of key personnel amounts to misrepresentation
FITZROY v ANGLO SWISS
The Technology and Construction Court held that failing to inform a customer of the forthcoming departure of a key team member amounted to fraudulent misrepresentation. It was also a possible breach of the duty to cooperate, which is implied into many, if not all, professional services contracts...more
   
September 2009 Drafting definitions and recitals requires care
OXONICA ENERGY v NEUFTEC (CA)
This decision concerned the interpretation of the definitions clause in a patent licence was at issue. The case has interesting implications for the drafting of commercial agreements and for the interpretation of the vast majority of existing commercial contracts...more
   
September 2009 Implied condition of satisfactory quality
BOMINFLOT v PETROPLUS
In relation to international sales contracts, the High Court clarified when the ‘term’ that goods will be of satisfactory quality implied by the Sale of Goods Act 1979 (SAGA) will apply in a free on board (FOB) contract and what that term means...more
   
July 2009 Excluding liability for deliberate breaches
INTERNET BROADCASTING CORPORATION (t/a NetTV) v MAR LLC
In this case, it was held that there is a presumption that a clause excluding liability for loss of profit should not cover liability arising from a deliberate decision to breach a contract (in this case a purported termination of a contract mid way through its term without cause) unless there was very clear and specific wording to show this was the parties’ intention...more
   

 

back to top